Number Description Project Type Status TIP Year
601347 BROCKTON- RECONSTRUCTION OF WINTER STREET, FROM HOWARD STREET TO NORTH CARY STREET (5,300 FEET - 3R PROJECT) Hwy Reconstr-No Added Capacity CONSTRUCTION
601393 BROCKTON- BRIDGE REPLACEMENT, B-25-060 (AVA), BARTLETT STREET OVER SALISBURY BROOK Bridge Replacement CONSTRUCTION
604431 BROCKTON- RECONSTRUCTION OF ROUTE 27, PLEASANT STREET AT WEST STREET AND WESTGATE MALL DRIVE Hwy. Reconstr - Minor Widening CONSTRUCTION
604595 BROCKTON- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 27, BELAIR STREET AND MORAINE STREET Traffic Signals CONSTRUCTION
604747 BROCKTON- BRIDGE BETTERMENT, B-25-048, ROUTE 123 (BELMONT STREET) OVER ROUTE 24 Structures Maintenance CONSTRUCTION
600365 BROCKTON- RESURFACING & RELATED WORK ON A SECTION OF ROUTE 27 (PLEASANT STREET & CRESCENT STREET) Resurfacing DESIGN 2012
601342 BROCKTON- RECONSTRUCTION OF COURT STREET, FROM MAIN STREET TO NORTH CARY STREET ("3R" PROJECT) Hwy Reconstr - Major Widening DESIGN
601344 BROCKTON- RECONSTRUCTION OF FOREST AVENUE, FROM WARREN AVENUE TO BELMONT STREET ("3R" PROJECT) Hwy Reconstr-No Added Capacity DESIGN
601346 BROCKTON- REHABILITATION OF ROUTE 123 (CENTRE STREET), FROM MONTELLO STREET TO NORTH CARY STREET (2,900 FEET - 3R PROJECT) Hwy Reconstr-No Added Capacity DESIGN
601639 BROCKTON- RESURFACING & RELATED WORK ON FIELD STREET, FROM MONTELLO STREET TO WINTER STREET (4,000 FT.) Resurfacing DESIGN
601642 BROCKTON- RESURFACING & RELATED WORK ON PERKINS AVENUE, FROM SUMMER STREET TO MAIN STREET (2,800 FT.) Resurfacing DESIGN
601644 BROCKTON- RESURFACING & RELATED WORK ON WEST ELM STREET, FROM WARREN AVENUE TO WEST STREET (6,800 FT.) Resurfacing DESIGN
602606 BROCKTON- SIGNAL UPGRADES AT ROUTE 123 (BELMONT STREET), V.A. HOSPITAL & THE ROUTE 123/MANLEY STREET INTERSECTION Traffic Signals DESIGN 2011
603675 BROCKTON- DOWNTOWN RECIRCULATION PROJECT (PHASE I) Hwy Reconstr-No Added Capacity DESIGN
604419 BROCKTON- BRIDGE REPLACEMENT, B-25-032, WHITE AVENUE OVER SALISBURY BROOK Bridge Replacement DESIGN
604741 BROCKTON- SIGNAL & INTERSECTION IMPROVEMENTS AT MAIN STREET (ROUTE 28) & PLAIN STREET/KEITH AVENUE Traffic Signals DESIGN 2011
605558 BROCKTON- WEST BRIDGEWATER- BRIDGEWATER- RAYNHAM- RESURFACING & RELATED WORK ON ROUTE 24 Resurfacing DESIGN
600004 BROCKTON- ROADWAY RECONSTRUCTION, BELMONT ST. (RT.123) @ PEARL ST; NORTH PEARL ST. (RT.27) @ OAK ST.; OAK ST. @ RESERVOIR ST. Hwy. Reconstr - Minor Widening COMPLETE
600422 BROCKTON- ROADWAY RECONSTRUCTION INCLUDING SIGNALS ON A SECTION OF ROUTE 123 (BELMONT STREET) Resurfacing COMPLETE
600649 BROCKTON- BRIDGE REPLACEMENT, BR# B-25-010 ALLEN STREET OVER SALISBURY BROOK (P.V. CHANGE ) Bridge Replacement COMPLETE
601338 BROCKTON- RESURFACING AND RELATED WORK ON NORTH MAIN STREET FROM PROSPECT STREET TO AVON T.L. (19,000 FEET) Resurfacing COMPLETE
601339 BROCKTON- ROADWAY RECONSTRUCTION ON WEST CHESTNUT ST. FROM PEARL ST. (STA. 1+00 METRIC) TO JUST WEST OF BURKE DRIVE (STA. 14+40) Hwy. Reconstr - Minor Widening COMPLETE
602539 BROCKTON- BRIDGE REPLACEMENT, BR# B-25-059 SPRING STREET OVER SALISBURY BROOK Bridge Replacement COMPLETE
602557 BROCKTON- SIGNAL & INTERSECTON IMPROVEMENTS AT ROUTE 28 (MONTELLO STREET) & ROUTE 37 (HOWARD STREET) Traffic Signals COMPLETE