Project Description:
PALMER- BRIDGE REPLACEMENT, BR# P-01-024, ROUTE 20 (PARK STREET) OVER CSX & ROUTE 67 NORTHBOUND
The existing bridge will be demolished and replaced with a new bridge approximately 100 feet to the south. The new bridge location provides a greater degree of safety through the provision of a straighter roadway alignment.
Location:
  • Town of Palmer
  • Construction Begins: Spring 2005
    Construction Ends: Summer 2008
    Resident Engineer: George Pelletier
    Construction Contract Value: $6,024,506.00
    Construction Bid Price: $5,276,279.00
    Initial Construction Estimate: $5,578,307.00
    MassHighway District: District 2
    Current Status: Bridge under construction. (as of 05/17/2006)
    Additional Info: Daily lane restrictions/reductions during the work week. All lanes open at end of work day and weekends. (as of 02/15/2008)

    Contracts (2) Progress
    # 30009 -- Design -- Bridge Rehab/Recon/New Const
    Palmer - Route 20 over Conrail and Route 67,BR# P-01-024 Final
    # 38898 -- Construction Contract
    Palmer - Bridge Replacement (P-1-24) Route 20 over Route 67 Terminated

    Bridges

    Contract Dates
    Notice to Proceed: 05/03/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction.
    Additional Info
    Daily lane restrictions/reductions during the work week. All lanes open at end of work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/09/1999
    Project Status Advertised 09/18/2004
    Project Status Advertised 12/18/2004
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 06/19/2001
    Highway Design Process 25% Comments to DE 08/15/2001
    Highway Design Process 25% Plans Complete 10/31/2002
    Highway Design Process Design Public Hearing 06/20/2002
    75% Design 75% Plans Received 02/19/2003
    75% Design 75% Comments to DE 05/27/2003
    25% 100% Plans Received 02/17/2004
    25% 100% Comments to DE 03/24/2004
    Final Design PS&E to FAPO 08/05/2004
    Final Design PS&E Received 12/09/2004
    Right of Way
    Certification Issued 09/13/2004
    Plans Accepted 06/23/2004
    Traffic
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 10/05/2004
    Wetlands Protection Act Permit Expires 10/05/2007
    ITS
    Utilities
    Non Participating