WEYMOUTH- IMPROVEMENTS AT ROUTE 53 (WASHINGTON STREET) & MIDDLE STREET
This project was initiated by a private developer as mitigation for their real estate development project. This roadway project includes improvement to the traffic signal at Route 53/Middle Street and a new signal installation at the intersection of Winter and Middle Streets. The road will be widened and new sidewalks, signs and pavement markings will be installed.
Location:
  • Town of Weymouth
  • Construction Begins: Spring 2011
    Construction Ends: Summer 2012
    Resident Engineer: Gene Lee
    Construction Contract Value: $2,376,450.00
    Construction Bid Price: $2,084,064.50
    Initial Construction Estimate: $2,286,683.07
    MassHighway District: District 6

    Contracts (4) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 67948 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) on Middle Street at Route 53 (Washington Street) and Winter Street. 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 04/15/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 10/26/2005
    Project Status Advertised 09/18/2010
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 08/21/2008
    Consultant Contract Process Workhours Approved 08/29/2008
    Consultant Contract Process NTP Issued 07/06/2009
    Design
    Highway Design Process 25% Plans Received 10/26/2009
    Highway Design Process 25% Comments to DE 03/31/2010
    Highway Design Process Design Public Hearing 09/30/1997
    Highway Design Process Design Public Hearing 04/07/2010
    75% Design 75% Plans Received 01/07/2002
    Final Design PS&E to FAPO 09/08/2010
    Final Design PS&E Received 08/24/2010
    Subsurface Exploration 100% Plans Received 07/07/2010
    Right of Way
    Certification Issued 09/15/2010
    Plans Received 07/13/2010
    Plans Comments to DE 07/13/2010
    Plans Accepted 07/15/2010
    Requirements Requirements 06/21/2010
    Advanced Title Exam Requested 03/05/2010
    Advanced Title Exam Completed 08/20/2010
    Registry Plans/Instruments Received 08/09/2010
    Registry Plans/Instruments Comments to DE 09/01/2010
    Traffic
    25% Design Review 25% Plans Received 11/03/2009
    25% Design Review 25% Plans Approved 11/17/2009
    75% Traffic Plans 75% Plans Received 07/12/2010
    75% Traffic Plans 75% Plans Approved 07/29/2010
    100% Traffic Plans 100% Plans Received 08/25/2010
    100% Traffic Plans 100% Plans Approved 09/09/2010
    Design Exceptions
    Regular Design Exception Approved 09/27/2010
    Regular Design Exception Submitted 06/14/2010
    Environmental
    Wetlands Protection Act Permit Issued 08/05/2010
    ITS
    Utilities
    Non Participating