CAMBRIDGE- BRIDGE REPLACEMENT, BR# C-01-013, WALDEN STREET OVER THE B & M RAILROAD AND MBTA
The purpose of this project is to replace the existing two span substandard bridge with a new two span continuous bridge. The historic brick arch cattle path will be rehabilitated. The proposed project limits on Walden Street extend from approximately the intersection of Richdale Avenue and Walden Street to approximately 15 feet beyond the intersection of King Street and Walden Street.
Location:
  • City of Cambridge
  • Construction Begins: Summer 2006
    Construction Ends: Autumn 2009
    Resident Engineer: Sean Magnus
    Construction Contract Value: $5,055,256.83
    Construction Bid Price: $4,184,918.25
    Initial Construction Estimate: $3,036,154.12
    MassHighway District: District 4

    Contracts (3) Progress
    # 45304 -- Construction Contract
    Cambridge - Bridge Rehabilitation (C-01-013) (Concrete) - Walden St. over the B&M RR and MBTA 100% Complete
    # 96044 -- Design -- Bridge Open End
    RD 3 F/A Non-NHS Bridges-Con O Final
    # 98125 -- Design -- Hwy Eng Open End
    Statewide - Assisting Highway Engineering Open - End Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/08/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/24/2005
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Complete 02/05/1999
    Highway Design Process Design Public Hearing 04/25/2000
    75% Design 75% Plans Received 01/27/2003
    75% Design 75% Comments to DE 05/23/2003
    25% 100% Plans Received 08/18/2003
    25% 100% Plans Received 04/27/2005
    25% 100% Plans Received 04/27/2005
    25% 100% Comments to DE 07/21/2004
    25% 100% Plans Complete 07/21/2004
    Final Design PS&E to CEPO 08/25/2005
    Final Design PS&E Received 08/25/2005
    Right of Way
    Certification Issued 09/16/2005
    Plans Accepted 05/18/2005
    Advanced Title Exam Requested 03/01/2005
    Registry Plans/Instruments Layout Schedule Sent 08/01/2005
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities