Project Description:
BERKLEY- DIGHTON- BRIDGE REPLACEMENT, B-08-001=D-08-011, ELM STREET (BERKLEY) CENTER STREET (DIGHTON) OVER THE TAUNTON RIVER
Location:
  • Town of Berkley
  • Town of Dighton
  • Construction Begins: Spring 2012
    Construction Ends: Spring 2015
    Resident Engineer: Aleksey Belov
    Construction Contract Value: $13,851,545.50
    Construction Bid Price: $12,511,061.80
    Initial Construction Estimate: $14,283,793.00
    MassHighway District: District 5
    Current Status: Backfilling West Abutment in progress. Crane for arch installation to arrive week of 9/15/14. Sidewalk installation. Partial lane closures are expected for crane erection and sidewalk installation. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 09/08/2014)

    Contracts (7) Progress
    # 36567 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 44055 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 54831 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71095 -- Construction Contract
    Bridge Replacement (B-08-001=D-08-011) (Steel) - Elm / Center Streets over the Taunton River. 50% Complete
    # 95057 -- Design -- MEPA/NEPA Compliance
    BERKLEY-DIGHTON BR-ENV STUDIES Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/06/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Backfilling West Abutment in progress. Crane for arch installation to arrive week of 9/15/14. Sidewalk installation. Partial lane closures are expected for crane erection and sidewalk installation. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/20/1975
    Project Status Initiated 01/23/2006
    Project Status Advertised 09/17/2011
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 11/07/2006
    Consultant Contract Process NTP Issued 02/09/2007
    Design
    Highway Design Process Design Public Hearing 09/18/2007
    75% Design 75% Plans Received 07/28/2010
    75% Design 75% Comments to DE 12/14/2010
    25% 100% Plans Received 07/11/2011
    25% 100% Comments to DE 08/15/2011
    Final Design PS&E to FAPO 09/13/2011
    Final Design PS&E Received 09/06/2011
    Right of Way
    Certification Issued 09/15/2011
    Requirements Requirements 05/25/2007
    Requirements Requirements 01/04/2008
    Traffic
    25% Design Review 25% Plans Received 08/04/2010
    25% Design Review 25% Plans Approved 08/23/2010
    75% Traffic Plans 75% Plans Received 08/04/2010
    75% Traffic Plans 75% Plans Approved 08/23/2010
    100% Traffic Plans 100% Plans Received 07/19/2011
    100% Traffic Plans 100% Plans Approved 07/26/2011
    100% Temp Signal 100% Plans Received 04/07/2008
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 11/03/2011
    Section 404 (ACOE) Permit Expires 11/30/2016
    Section 401 (WQC) Permit Issued 05/08/2008
    Coast Guard Permit Issued 12/16/2011
    ITS
    Utilities
    Non Participating