Project Description:
BRAINTREE- ROADWAY RECONSTRUCTION AT CHURCH AND ELM STREETS (PHASE II)
Location:
  • Town of Braintree
  • Construction Begins: Summer 1999
    Construction Ends: Spring 2002
    Resident Engineer: Tom Reynolds
    Construction Contract Value: $1,191,640.84
    Construction Bid Price: $879,816.79
    Initial Construction Estimate: $1,000,974.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 99071 -- Construction Contract
    CHURCH ST AND ELM ST RESON (PHASE II) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/30/1999
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 02/22/1994
    Project Review Committee PRC Approved 03/08/1994
    Project Status Advertised 07/25/1998
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Regular Design Exception Approved 07/08/1998
    Environmental
    ITS
    Utilities
    Non Participating