| Project Description: |
RANDOLPH- ROADWAY RECONSTRUCTION ON ROUTE 139 (UNION STREET) FROM ROUTE 28 TO MILL STREET
The work consists of reconstructing Union Street and includes new drainage pipes and structures, granite curbing and cement sidewalks. New traffic signs will be also be installed.
|
| Location: |
|
| Construction Begins: | Summer 2002 |
| Construction Ends: | Summer 2004 |
| Resident Engineer: | Reginald Jacobs, Jr![]() |
| Construction Contract Value: | $1,776,061.65 |
| Construction Bid Price: | $1,388,252.50 |
| Initial Construction Estimate: | $1,388,946.50 |
| MassHighway District: | District 4 |
| Current Status: | This project is complete. (as of 02/25/2005) |
|