Project Description:
DOVER- NEEDHAM- BRIDGE REPLACEMENT, BR# D-10-002=N-04-009 DOVER ROAD OVER THE CHARLES RIVER
Location:
  • Town of Dover
  • Town of Needham
  • Construction Begins: Winter 2000/2001
    Construction Ends: Autumn 2002
    Resident Engineer: Brian McKenney
    Construction Contract Value: $1,154,491.00
    Construction Bid Price: $1,091,691.00
    Initial Construction Estimate: $1,036,000.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 31159 -- Construction Contract
    Bridge Replacement (Concrete) - Dover Road/Charles River Street over the Charles River. 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 02/14/2001
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 06/08/1995
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 10/21/2000