| Project Description: |
BOSTON- BRIDGE REPLACEMENT, BR# B-16-034 SUMMER STREET OVER RESERVE CHANNEL
|
| Location: |
|
| Construction Begins: | Spring 1998 |
| Construction Ends: | Summer 2003 |
| Resident Engineer: | Thomas Manning![]() |
| Construction Contract Value: | $15,723,647.86 |
| Construction Bid Price: | $12,956,297.50 |
| Initial Construction Estimate: | $14,174,019.50 |
| MassHighway District: | District 4 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||