Project Description:
BOSTON- BRIDGE REPLACEMENT, BR# B-16-034 SUMMER STREET OVER RESERVE CHANNEL
Location:
  • City of Boston
  • Construction Begins: Spring 1998
    Construction Ends: Summer 2003
    Resident Engineer: Thomas Manning
    Construction Contract Value: $15,723,647.86
    Construction Bid Price: $12,956,297.50
    Initial Construction Estimate: $14,174,019.50
    MassHighway District: District 4

    Contracts (1) Progress
    # 98182 -- Construction Contract
    Bridge Replacement (Prestressed Concrete) - Summer Street over Reserve Channel. 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/05/1998
    Contract Information
    Project Designer: Municipality
    Funding Source: BR. REPL. ON SYSYEM URBAN
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 05/03/1994
    Project Review Committee PRC Approved 05/24/1994
    Project Status Advertised 05/03/1997
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating