Project Description:
DEDHAM- BRIDGE REHABILITATION, D-05-004, ROUTE 109 (BRIDGE STREET) OVER THE CHARLES RIVER
This project will replace the Route 109 over the Charles River bridge superstructure and its supporting abutments. It will include the construction of new concrete abutments supported by steel piles and new piers supported by concrete piles. The approach roadway from approximately 725 feet towards west and 500 feet towards east will also be reconstructed. Westbound traffic will be maintained by a temporary bridge and Eastbound traffic will use half the bridge during construction. Pedestrians will be required to use the temporary bridge during construction.
Location:
  • Town of Dedham
  • Construction Begins: Winter 2008/2009
    Construction Ends: Autumn 2011
    Resident Engineer: Ayobami Akinade
    Construction Contract Value: $5,665,875.00
    Construction Bid Price: $4,926,123.00
    Initial Construction Estimate: $4,558,120.50
    MassHighway District: District 4
    Current Status: Performed static load test on test pile. Cintinued to drill and install micropiles. Utility work is now complete. (as of 08/03/2010)

    Contracts (4) Progress
    # 30270 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 57634 -- Construction Contract
    Bridge Rehabilitation (D-05-004) (Concrete) - Route 109 (Bridge Street) over the Charles River. 35% Complete
    # 94011 -- Design -- Bridge Rehab/Recon/New Const
    DEDHAM-ROUTE 109/CHARLES RIVER Final
    # 97043 -- Design -- Bridge Open End
    Rd2 Brd FA NHS/NON-NHS CONT. A Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/18/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REHABILITATION
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Performed static load test on test pile. Cintinued to drill and install micropiles. Utility work is now complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 01/18/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 07/19/2008
    Project Status Advertised 09/13/2008
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 10/21/1997
    Design
    Highway Design Process 25% Plans Received 05/08/2000
    Highway Design Process 25% Comments to DE 03/13/2001
    25% 75% Plans Received 12/28/2001
    25% 75% Comments to DE 07/28/2003
    75% 100% Plans Received 06/05/2006
    75% 100% Plans Received 05/08/2007
    75% 100% Comments to DE 07/26/2006
    75% 100% Comments to DE 08/06/2007
    Subsurface Exploration PS&E to CEPO 12/26/2007
    Subsurface Exploration PS&E Received 12/19/2007
    Right of Way
    Certification Issued 08/09/2007
    Plans Accepted 05/15/2006
    Requirements Requirements 11/23/2005
    Advanced Title Exam Requested 04/03/2006
    Registry Plans/Instruments Layout Schedule Sent 08/08/2006
    Traffic
    100% Design Review 100% Plans Received 06/06/2006
    100% Design Review 100% Plans Approved 06/20/2006
    100% Traffic Plans 100% Plans Received 06/06/2006
    100% Traffic Plans 100% Plans Approved 06/20/2006
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 09/05/2006
    Section 404 (ACOE) Permit Expires 01/20/2010
    Section 401 (WQC) Permit Issued 06/30/2006
    Section 401 (WQC) Permit Expires 01/20/2010
    ITS
    Utilities
    Non Participating