Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROOKLINE- SAFETY IMPROVEMENTS, BEACON STREET FROM ST. MARY'S STREET TO THE BOSTON CL (2.25 MILES)
The proposed project will update existing signals, install new signals, and result in an increased corridor capacity for Beacon Street and the MBTA green line. The work will include the installation of new signals and modifications to the existing signals, installation of wheelchair ramps, reconstruction of existing parking areas, and the provision of various amenities.
Location:
  • Town of Brookline
  • Construction Begins: Autumn 2005
    Construction Ends: Spring 2008
    Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $15,047,090.10
    Construction Bid Price: $15,796,444.00
    Initial Construction Estimate: $11,507,912.93
    MassHighway District: District 4
    Current Status: Punch list work is ongoing including wheelchair ramps and sidewalks and traffic signal walk up pads. (as of 09/25/2009)

    Contracts (1) Progress
    # 42420 -- Construction Contract
    Brookline - Traffic Safety Improvements on a Section of Beacon Street 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/24/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Punch list work is ongoing including wheelchair ramps and sidewalks and traffic signal walk up pads.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/25/1995
    Project Review Committee Received 01/27/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 09/18/2004
    Project Status Advertised 02/19/2005
    Project Status Advertised 07/09/2005
    Prj Scope & Negotiation
    Design
    25% Design 25% Plans Received 12/02/1997
    25% Design 25% Comments to DE 05/11/1998
    75% Design 75% Plans Received 08/28/2003
    75% Design 75% Plans Approved 03/16/2004
    75% Design 75% Comments to DE 03/04/2004
    100% Design 100% Plans Received 06/07/2004
    100% Design 100% Plans Complete 09/01/2004
    Final Design PS&E to CEPO 08/05/2004
    Final Design PS&E Received 08/05/2004
    Right of Way
    Certification Issued 08/23/2004
    Traffic
    100% Design Review 100% Plans Received 02/01/2005
    100% Design Review 100% Plans Approved 03/03/2005
    100% Traffic Plans 100% Plans Received 02/01/2005
    100% Traffic Plans 100% Plans Approved 03/03/2005
    100% TMP 100% Plans Approved 06/04/2004
    100% TCA 100% Plans Received 03/04/2005
    100% TCA 100% Plans Approved 02/07/2005
    Design Exceptions
    Regular Design Exception Approved 06/06/2000
    Regular Design Exception Approved 08/29/2000
    Environmental
    ITS
    Utilities
    Non Participating