Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHELSEA- RECONSTRUCTION, EASTERN AVENUE FROM CENTRAL AVENUE TO BROADWAY (7,000 FEET)
This project will result in the reconstruction of Eastern Avenue and the provision of sidewalks, drainage improvements, and various pedestrian amenities.
Location:
  • City of Chelsea
  • Construction Begins: Winter 2004/2005
    Construction Ends: Summer 2008
    Resident Engineer: Nick Delvento
    Construction Contract Value: $9,556,062.75
    Construction Bid Price: $6,988,098.50
    Initial Construction Estimate: $6,766,119.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 36919 -- Construction Contract
    Chelsea - Eastern Avenue, Roadway Reconstruction 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/16/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 02/22/1995
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 07/24/2004
    Prj Scope & Negotiation
    Design
    100% Design 100% Plans Received 03/30/2004
    100% Design 100% Comments to DE 06/02/2004
    Final Design PS&E to CEPO 07/14/2004
    Final Design PS&E Received 07/14/2004
    Right of Way
    Certification Issued 06/14/2004
    ROW STATUS Section Cleared 06/14/2004
    Traffic
    Design Exceptions
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 08/18/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 11/20/2003
    Regular Design Exception Approved 09/14/2004
    Environmental
    ITS
    Utilities
    Non Participating