| Project Description: |
MILTON- CONSTRUCTION OF A CHEMICAL STORAGE BUILDING AT MHD MAINTENANCE DEPOT AT 73 GRANITE AVENUE
CONSTRUCTION OF A CHEMICAL ( SALT ) STORAGE BUILDING AT MHD MAINTENANCE DEPOT AT 73 GRANITE AVENUE IN MILTON
|
| Location: |
|
| Construction Begins: | Summer 2003 |
| Construction Ends: | Summer 2004 |
| Resident Engineer: | Brian Zilinsky![]() |
| Construction Contract Value: | $1,154,095.00 |
| Construction Bid Price: | $1,134,195.00 |
| Initial Construction Estimate: | $854,190.00 |
| MassHighway District: | District 4 |
| Current Status: | Work under this contract consists of the construction of a chemical storage building with snow and ice office: demolition and disposal of two existing storage sheds : bituminous concrete excavation and resurfacing: construction of new entrance with gate: drainage pipe and berm: removal and resetting of calcium chloride pump. The majority of the work has been completed with just punch list items remaining. (as of 05/31/2005) |
| Additional Info: | The finals Package on this project will be submitted soon. (as of 05/31/2005) |
|