Project Description:
GILL- MONTAGUE- BRIDGE REHABILITATION, G-04-010=M-28-031, AVENUE A OVER CONNECTICUT RIVER & REPAIR OF G-12-020=M-28-001, MONTAGUE CITY ROAD OVER THE CONNECTICUT RIVER
The work included in this project involves the rehabilitation of the existing steel truss structure carrying Avenue A over the Connecticut River. The bridge will be rehabilitated and restored in the existing location and will provide wider travel lanes and bicycle accessibility. The roadway bridge approaches will be resurfaced. There will be geometric improvements and new traffic signal equipment installed at the Route 2/Avenue A/Main Street intersection. Bridge traffic will be maintained only in the southbound lane toward Turner Falls during construction with outbound northerly traffic being redirected through Greenfield Route 2A to Route 2 East/West.
Location:
  • Town of Gill
  • Town of Montague
  • Construction Begins: Winter 2009/2010
    Construction Ends: Spring 2014
    Resident Engineer: Robert Demers
    Construction Contract Value: $46,829,790.00
    Construction Bid Price: $40,726,536.50
    Initial Construction Estimate: $40,194,820.50
    MassHighway District: District 2

    Contracts (6) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54825 -- Design -- Hwy Eng Open End
    Work will consist of providing design and review services to MassHighway on an open end basis for various statewide highway and bridge projects Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59992 -- Construction Contract
    2 Bridges over CT River: GILL - MONTAGUE, Reconstruction (G-04-010=M-28-031) (Steel) Avenue A. GREENFIELD - MONTAGUE, Repair (G-12-20=M-28-001) (Steel) Montague City Road. 95% Complete
    # 69761 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 98185 -- Design -- Bridge Rehab/Recon/New Const
    GILL- MONTAGUE- BRIDGE REHABILITATION, BR# G-04-010-M-28-031 TURNERS FALLS ROAD OVER CONNECTICUT RIVER Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/11/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/22/1995
    Project Review Committee Received 09/25/1995
    Project Review Committee PRC Approved 10/03/1995
    Project Status Advertised 09/20/2008
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 06/03/2003
    Highway Design Process 25% Comments to DE 09/05/2003
    Highway Design Process Design Public Hearing 04/27/2004
    25% 75% Plans Received 03/20/2006
    25% 75% Comments to DE 09/20/2006
    75% 100% Plans Received 05/08/2008
    75% 100% Comments to DE 07/15/2008
    Subsurface Exploration PS&E to FAPO 09/16/2008
    Subsurface Exploration PS&E Received 09/10/2008
    Right of Way
    Certification Issued 09/08/2008
    Plans Accepted 03/27/2008
    Requirements Requirements 01/22/2008
    Advanced Title Exam Requested 02/01/2008
    Registry Plans/Instruments Requested 08/28/2008
    Traffic
    75% Design Review 75% Plans Received 03/20/2006
    75% Design Review 75% Plans Approved 08/25/2006
    75% Traffic Plans 75% Plans Received 03/20/2006
    75% Traffic Plans 75% Plans Approved 08/25/2006
    75% Draft Temp Signal 75% Plans Received 03/20/2006
    75% Draft Temp Signal 75% Plans Approved 08/25/2006
    100% Traffic Plans 100% Plans Received 05/12/2008
    100% Traffic Plans 100% Plans Approved 05/22/2008
    100% Temp Signal 100% Plans Received 05/12/2008
    100% Temp Signal 100% Plans Approved 05/22/2008
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating