WESTON- BRIDGE REPLACEMENT, W-29-001, MERRIAM STREET OVER B&M RAILROAD & MBTA
The proposed project consists of replacing the existing wooden deck bridge with a concrete beam bridge approximately 50 feet to the east. The project will also involve the reconstruction of Merriam Street from 200 feet south of Hallett Hill Road to 165 feet north of Granison Road, cement concrete sidewalks, installation of steel beam guardrail, and other incidental items of work.
Location:
  • Town of Weston
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Construction Begins: Winter 2013/2014
    Project Manager: Marie Rose
    Estimated Construction Cost: $1,000,000.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 96043 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON A Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 12/30/1996
    Project Review Committee PRC Approved 12/11/1995
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating