| Project Description: |
WESTON- BRIDGE REPLACEMENT, W-29-001, MERRIAM STREET OVER B&M RAILROAD & MBTA
The proposed project consists of replacing the existing wooden deck bridge with a concrete beam bridge approximately 50 feet to the east. The project will also involve the reconstruction of Merriam Street from 200 feet south of Hallett Hill Road to 165 feet north of Granison Road, cement concrete sidewalks, installation of steel beam guardrail, and other incidental items of work.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Other |
| Construction Begins: | Winter 2013/2014 |
| Project Manager: | Marie Rose![]() |
| Estimated Construction Cost: | $1,000,000.00 |
| MassHighway District: | District 4 |
| Current Status: | This project is in the preliminary design phase. |
|