Project Description:
NEWTON- WATERTOWN- RECONSTRUCTION OF PLEASANT STREET & HOWARD STREET (6,280 FT. TOTAL)
Reconstruction of Pleasant Street from the Waltham city line easterly to Main Street (Route 20) at Watertown Square, a distance of approximately 8,080 feet; and Howard Street from Pleasant Street northerly to Main Street (Route 20), a distance of approximately 1,000 feet. The project will include six signalized locations at intersections of Pleasant with Stop & Shop Driveway, Commonwealth of MA driveway, Bridge Street, Rosedale Road, Myrtle Street, and at Pedestrian Crossing approximately 450 feet east of Paramont Place.
Location:
  • City of Newton
  • Town of Watertown
  • Construction Begins: Winter 2008/2009
    Construction Ends: Summer 2011
    Resident Engineer: Gennady Shkolnikov
    Construction Contract Value: $8,844,104.69
    Construction Bid Price: $7,596,267.00
    Initial Construction Estimate: $7,627,164.50
    MassHighway District: District 4
    Current Status: utility relocation by others. Contractor building retaining wall. (as of 08/04/2010)

    Contracts (1) Progress
    # 56954 -- Construction Contract
    Newton-Watertown - Roadway Reconstruction and Related Work on Pleasant Street and Howard Street, PF #601686 80% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/13/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    utility relocation by others. Contractor building retaining wall.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/29/1995
    Project Review Committee Received 12/04/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Review Committee Letter 02/14/1996
    Project Status Advertised 07/19/2008
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 06/18/1997
    Highway Design Process 25% Comments to DE 10/21/1997
    Highway Design Process Design Public Hearing 12/08/1999
    75% Design 75% Plans Received 10/15/2002
    75% Design 75% Comments to DE 01/21/2005
    100% Design 100% Plans Received 01/09/2007
    100% Design 100% Comments to DE 06/14/2007
    Final Design PS&E to CEPO 04/17/2008
    Final Design PS&E Received 02/08/2008
    Right of Way
    Certification Issued 04/02/2008
    Requirements Requirements 11/14/2003
    Requirements Requirements 01/14/2005
    Requirements Requirements 10/25/2005
    Requirements Requirements 01/18/2007
    Traffic
    100% Design Review 100% Plans Received 01/09/2007
    100% Design Review 100% Plans Approved 05/21/2007
    100% Traffic Plans 100% Plans Received 01/09/2007
    100% Traffic Plans 100% Plans Approved 05/21/2007
    100% Temp Signal 100% Plans Received 01/09/2007
    100% Temp Signal 100% Plans Approved 05/21/2007
    100% TCA 100% Plans Received 02/20/2008
    100% TCA 100% Plans Approved 03/24/2008
    Design Exceptions
    Regular Design Exception Approved 06/09/1998
    Regular Design Exception Approved 10/08/1999
    Environmental
    ITS
    Utilities
    Non Participating