Project Description:
NEWTON- ROADWAY WIDENING, DRAINAGE & SIGNAL UPGRADE, WALNUT STREET, AND CENTER ST. TO RTE. 9
This project includes upgrading the traffic signals at the intersection of Walnut Street and Center Street; reconstructing Walnut Street from Center Street to Route 9; and reconstructing Center Street from Walnut Street to Route 9.
Location:
  • City of Newton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Construction Begins: Winter 2011/2012
    Project Manager: David Shedd
    Estimated Construction Cost: $3,000,000.00
    MassHighway District: District 4
    Current Status: The 25% project plan submission has been returned to the Design Engineer for revisions and resubmission. (as of 06/15/1998)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/06/1995
    Project Review Committee Received 12/07/1995
    Project Review Committee PRC Approved 02/06/1996
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 05/27/1998
    Highway Design Process 25% Plans Rejected 06/15/1998
    Right of Way
    Requirements Requirements 11/29/2005
    Traffic
    Design Exceptions
    Regular Design Exception Approved 11/24/1997
    Environmental
    ITS
    Utilities
    Non Participating