Project Description:
SOMERVILLE- RECONSTRUCTION OF BEACON STREET, FROM OXFORD STREET TO CAMBRIDGE C.L. (1.1 MILES)
This project consists of reconstructing Beacon Street from the Cambridge city line to Oxford Street. New sidewalks, curbing, drainage and signal improvements are included in the project.
Location:
  • City of Somerville
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2013
    Project Manager: Shawn Holland
    Estimated Construction Cost: $3,900,000.00
    Funding Provision: This project is planned to be funded through the 2013 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    MassHighway District: District 4
    Current Status: Comments on the 75% design phase project plans have been returned to the Design Engineer (as of 11/23/2004)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2013
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: SOMERVILLE
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category HIGH PRIORITY PROJECTS
    Federal Cost: $2,064,248.00
    State Cost: $516,062.00
    Total Cost: $2,580,310.00
    Category SURFACE TRANSPORTATION PROGRAM - OTHER AREAS
    Federal Cost: $1,055,200.00
    State Cost: $263,800.00
    Total Cost: $1,319,000.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/13/1996
    Project Review Committee Received 03/14/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Review Committee Letter 09/06/1996
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 03/01/1999
    Highway Design Process 25% Comments to DE 10/22/1999
    Highway Design Process Design Public Hearing 11/08/1999
    75% Design 75% Plans Received 03/25/2004
    75% Design 75% Comments to DE 11/23/2004
    Right of Way
    Requirements Requirements 11/01/2005
    Traffic
    75% Design Review 75% Plans Approved 11/17/2004
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating