| Project Description:
|
BOSTON- TRAFFIC SIGNAL SYSTEM COMPUTER UPGRADE PROJECT AT BOSTON CITY HALL
|
| Location:
|
City of Boston
|
| Construction Begins:
|
Spring 2001 |
| Construction Ends:
|
Spring 2006 |
| Resident Engineer:
|
Ahmad Ilyas |
| Construction Contract Value:
|
$5,959,000.00 |
| Construction Bid Price:
|
$3,300,000.00 |
| Initial Construction Estimate:
|
$3,299,000.00 |
| MassHighway District:
|
District 4 |
| Current Status:
|
System is on final testing. All physical work has been completed. The resident engineer still expects completion and acceptance by June 30, 2005 (as of 05/23/2005) |