Project Description:
NEEDHAM- RECONSTRUCTION OF HIGHLAND AVENUE, FROM WEBSTER STREET TO THE NEEDHAM/NEWTON LINE
The purpose of widening Highland Avenue is to provide two lanes in each direction. Exclusive left-turn lanes are proposed at the Second Avenue signalized intersection. A sidewalk is proposed for the entire length of the project along both sides of Highland Avenue. Bicycles will be accommodated with a minimum width curb lane on both sides of Highland Avenue. A new traffic signal will be installed and the existing traffic signal systems will be upgraded to improve the level of service. The design and construction of these improvements are required for the increased traffic volumes associated with the future growth of the Town of Needham.
Location:
  • Town of Needham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2014
    Project Manager: Thomas H Currier
    Estimated Construction Cost: $4,354,640.00
    Total Estimated Project Cost: $2,100,000.00
    MassHighway District: District 4
    Current Status: 25% Project Plans have been received. (as of 03/29/2010)

    Contracts (1) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/02/1996
    Project Review Committee Received 04/04/1996
    Project Review Committee PRC Approved 08/20/1996
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 05/15/2009
    Design
    Highway Design Process 25% Plans Received 03/29/2010
    Highway Design Process 25% Comments to DE 03/18/2005
    Right of Way
    Plans Received 04/06/2010
    Requirements Requirements 04/06/2010
    Traffic
    25% Design Review 25% Plans Received 04/05/2010
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating