Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-053 & REHABILITATION, P-10-060, HUNGERFORD STREET OVER S.W. BRANCH OF THE HOUSATONIC RIVER
Two separate bridges approximately one-half mile apart will be replaced at their respective locations with approach roadway improvements. The Hungerford Street bridge north of Route 20 will be replaced by a 18.3-meter long precast bridge with a concrete deck slab. The Hungerford Street Bridges crossing the South West Branch of the Housatonic River will be replaced with a new 9.1-meter long precast concrete bridge with a concrete deck. Both bridges will provide two 3.7-meter travel lanes and two 1.5-meter sidewalks.
Location:
  • City of Pittsfield
  • Construction Begins: Summer 2008
    Construction Ends: Summer 2010
    Resident Engineer: Michael Cullett
    Construction Contract Value: $2,501,887.00
    Construction Bid Price: $2,451,967.00
    Initial Construction Estimate: $2,385,768.00
    MassHighway District: District 1

    Contracts (3) Progress
    # 55843 -- Construction Contract
    Pittsfield - 2 Bridge Replacements Br. Nos P-10-053 and P-10-060 Both on Hungerford Street both over the SW Branch of the Housatonic River 79% Complete
    # 95254 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTC Final
    # 99050 -- Design -- Bridge Rehab/Recon/New Const
    PITTSFIELD- BRIDGE REPLACEMENT, BR# P-10-053 & BRIDGE REHABILITATION BR# P-10-060 HUNGERFORD ST. OVER S.W. BR. HOUSATONIC RIVER Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/18/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/21/1996
    Project Review Committee Received 08/05/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Review Committee Letter 09/12/1996
    Project Status Advertised 05/10/2008
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 02/04/1997
    Consultant Contract Process NTP Issued 05/19/1997
    Design
    Highway Design Process 25% Plans Received 10/20/1997
    Highway Design Process 25% Comments to DE 03/02/1998
    Highway Design Process Design Public Hearing 03/16/1998
    75% Design 75% Plans Received 07/26/2001
    25% 100% Plans Received 10/02/2006
    25% 100% Comments to DE 01/18/2007
    Final Design PS&E to CEPO 05/06/2008
    Final Design PS&E Received 01/23/2008
    Right of Way
    Certification Issued 02/28/2008
    Requirements Requirements 12/15/2005
    Requirements Requirements 01/05/2006
    Requirements Requirements 01/12/2006
    Requirements Requirements 11/13/2006
    Traffic
    100% Design Review 100% Plans Received 10/05/2006
    100% Design Review 100% Plans Approved 10/24/2006
    100% Traffic Plans 100% Plans Received 10/05/2006
    100% Traffic Plans 100% Plans Approved 10/24/2006
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 02/01/2008
    Section 404 (ACOE) Permit Expires 01/20/2010
    Section 401 (WQC) Permit Issued 01/04/2008
    ITS
    Utilities
    Non Participating