DEDHAM- RECONSTRUCTION OF WASHINGTON STREET, FROM PROVIDENCE HIGHWAY CIRCLE TO BOSTON C.L. (1130 METERS) INCLUDES D-05-008
This is an Urban Principal Arterial NON - NHS Discontinuance project currently maintained by District Four. The project consists of full depth reconstruction including removal of trolley tracks, landscaping, upgraded drainage. Once the project is complete, ownership of the roadway will be transferred to the Town of Dedham.
Location:
  • Town of Dedham
  • Construction Begins: Spring 2009
    Construction Ends: Autumn 2011
    Resident Engineer: Mark Spinale
    Construction Contract Value: $6,689,274.00
    Construction Bid Price: $6,937,083.00
    Initial Construction Estimate: $7,464,378.00
    MassHighway District: District 4
    Current Status: Working on Bridge over Mother Brook. (as of 07/27/2010)

    Contracts (1) Progress
    # 57755 -- Construction Contract
    Road Reconstruction and Related Work on a Section of Washington Street. 75% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 03/25/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Working on Bridge over Mother Brook.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/22/1996
    Project Review Committee Received 10/22/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Status Advertised 09/20/2008
    Project Status Advertised 01/24/2009
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 01/05/2004
    Highway Design Process 25% Comments to DE 06/25/2004
    Highway Design Process Design Public Hearing 12/07/2004
    75% Design 75% Plans Received 09/06/2005
    75% Design 75% Comments to DE 06/05/2006
    100% Design 100% Plans Received 10/16/2007
    100% Design 100% Comments to DE 04/16/2008
    Final Design PS&E to CEPO 09/16/2008
    Final Design PS&E Received 07/16/2008
    Right of Way
    Certification Issued 09/16/2008
    Plans Received 09/05/2008
    Plans Accepted 11/09/2005
    Requirements Requirements 07/07/2005
    Advanced Title Exam Requested 11/10/2005
    Advanced Title Exam Completed 06/02/2008
    Registry Plans/Instruments Requested 05/14/2008
    Registry Plans/Instruments Received 08/21/2008
    Registry Plans/Instruments Comments to DE 08/28/2008
    Traffic
    75% Design Review 75% Plans Received 10/18/2005
    75% Design Review 75% Plans Approved 11/17/2005
    75% Traffic Plans 75% Plans Received 10/18/2005
    75% Traffic Plans 75% Plans Approved 11/17/2005
    75% Draft Temp Signal 75% Plans Received 10/18/2005
    75% Draft Temp Signal 75% Plans Approved 11/17/2005
    100% Traffic Plans 100% Plans Received 10/17/2007
    100% Traffic Plans 100% Plans Approved 01/22/2008
    100% Temp Signal 100% Plans Received 10/17/2007
    100% Temp Signal 100% Plans Approved 01/22/2008
    Design Exceptions
    Regular Design Exception Approved 01/15/2003
    Environmental
    Section Cleared 25% Plans Received 07/21/2005
    Section Cleared 25% Comments to DE 11/03/2005
    Wetlands Protection Act Permit Issued 06/06/2008
    Wetlands Protection Act Permit Expires 06/06/2011
    ITS
    Utilities
    Non Participating