DEDHAM- INTERSECTION & SIGNAL IMPROVEMENTS AT HIGH STREET, HARRIS STREET, WASHINGTON STREET & BRYANT STREET (PHASE II)
The proposed project consists of safety and traffic improvements at the following intersections: High Street and Washington Street; Washington Street and Harris Street; and High Street and Eastern Avenue.
Location:
  • Town of Dedham
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Construction Begins: Autumn 2012
    Project Manager: Brian Fallon
    Estimated Construction Cost: $0.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/22/1996
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating