Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WILLIAMSTOWN- BRIDGE REPLACEMENT, W-37-017, ROUTE 43 OVER THE GREEN RIVER
The work consists of the replacement of the Route 43 (Green River Road) bridge over the Green River with a single span concrete bridge. The proposed bridge width will be 26 feet curb to curb. Also included is roadway approach work, guardrail, pavement markings and signing.
Location:
  • Town of Williamstown
  • Construction Begins: Spring 2008
    Construction Ends: Winter 2009/2010
    Resident Engineer: Glenn Cellana
    Construction Contract Value: $1,584,811.00
    Construction Bid Price: $1,369,729.00
    Initial Construction Estimate: $1,431,674.00
    MassHighway District: District 1
    Current Status: Bridge is open to traffic. Contractor is working on signs. (as of 09/23/2009)

    Contracts (2) Progress
    # 34008 -- Design -- Hwy Eng Open End
    Provide engineering design and review services on an open end basis for various highway and bridge projects. Final
    # 54112 -- Construction Contract
    Williamstown - Bridge Replacement (W-37-017) - Route 43 (Green River Road) over the Green River 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 03/26/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge is open to traffic. Contractor is working on signs.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/05/1997
    Project Review Committee Received 02/10/1997
    Project Review Committee PRC Approved 02/25/1997
    Project Review Committee Letter 03/21/1997
    Project Status Advertised 09/15/2007
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 07/25/1997
    Consultant Contract Process Workhours Approved 11/10/1997
    Consultant Contract Process NTP Issued 02/25/1998
    Design
    Highway Design Process 25% Plans Received 10/21/1998
    Highway Design Process 25% Comments to DE 02/26/2004
    Highway Design Process Design Public Hearing 04/29/2004
    75% Design 75% Plans Received 06/01/2006
    75% Design 75% Comments to DE 02/28/2007
    25% 100% Plans Received 03/15/2007
    25% 100% Comments to DE 06/28/2007
    Final Design PS&E to CEPO 09/10/2007
    Final Design PS&E Received 08/01/2007
    Right of Way
    Certification Issued 09/07/2007
    Plans Accepted 04/05/2007
    Requirements Requirements 10/18/2005
    Advanced Title Exam Completed 11/15/2006
    Registry Plans/Instruments Layout Schedule Sent 08/22/2007
    Traffic
    25% Design Review 25% Plans Received 06/01/1999
    25% Design Review 25% Plans Approved 09/02/1999
    75% Design Review 75% Plans Received 06/08/2006
    75% Design Review 75% Plans Approved 07/19/2006
    75% Traffic Plans 75% Plans Received 06/08/2006
    75% Traffic Plans 75% Plans Approved 07/19/2006
    100% Design Review 100% Plans Received 03/15/2007
    100% Design Review 100% Plans Approved 04/04/2007
    100% Traffic Plans 100% Plans Received 03/15/2007
    100% Traffic Plans 100% Plans Approved 04/04/2007
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 03/14/2007
    Section 404 (ACOE) Permit Expires 01/20/2010
    Section 401 (WQC) Permit Issued 04/12/2007
    Section 401 (WQC) Permit Expires 01/20/2010
    ITS
    Utilities
    Non Participating