Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MILTON- QUINCY- CONSTRUCTION OF NOISE BARRIER ALONG SECTIONS OF ROUTE I-93 (CONTRACT #2)
Location:
  • Town of Milton
  • City of Quincy
  • Construction Begins: Autumn 1999
    Resident Engineer: Reginald Jacobs, Jr
    Construction Contract Value: $2,903,174.00
    Construction Bid Price: $2,528,340.00
    Initial Construction Estimate: $2,461,275.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 30113 -- Construction Contract
    I-93 NOISE BARRIER INSTALLATION (#2) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/17/1999
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 01/09/1999
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating