Project Description:
QUINCY- TRAFFIC SIGNAL INSTALLATION AND INTERSECTION IMPROVEMENTS, HANCOCK ST/SOUTHERN ARTERY
The proposed project consists of the reconstruction of Hancock Street from approximately 100 feet south of Saint Ann's Road extending northerly approximately 1,400 feet to approximately 90 feet north of Fenno St. In addition, approximately 320 feet of Merrymount Parkway will be reconstructed east of its intersection with Hancock St. Under this project, minor portions (less than 40 feet) of Saint Ann's Road, Standish Avenue and Fenno Street will also be constructed. The intersection of Merrymount Parkway at Hancock Street will be reconstructed to eliminate the high speed right turn lane westbound and increase the distance between Merrymount Parkway and Standish Avenue. A new, fully actuated traffic signal is proposed at the intersection of Hancock Street at Merrymount Parkway as well as at Hancock Street at St. Ann's Road to address safety concerns and reduce congestion along the corridor. New sidewalks are proposed along the entire easterly side of the road within the project area and along the westerly side of Hancock Street from Merrymount Parkway to Standish Ave. New pavement markings will be installed to delineate travel lanes, providing additional width for bicyclists within the outside travel lanes.
Location:
  • City of Quincy
  • Construction Begins: Winter 2004/2005
    Construction Ends: Winter 2006/2007
    Resident Engineer: Lonardi Philogene
    Construction Contract Value: $1,065,181.00
    Construction Bid Price: $898,640.00
    Initial Construction Estimate: $807,471.00
    MassHighway District: District 4
    Current Status: This project is completed and has been submitted to finals. (as of 10/01/2007)

    Contracts (1) Progress
    # 37968 -- Construction Contract
    Traffic Safety Improvements - Hancock Street at Merrymount Parkway. 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/07/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is completed and has been submitted to finals.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/11/1997
    Project Review Committee Received 06/18/1997
    Project Review Committee PRC Approved 07/15/1997
    Project Status Advertised 09/18/2004
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Approved 05/13/2004
    Highway Design Process 25% Plans Complete 05/26/2004
    Final Design PS&E to CEPO 08/27/2004
    Final Design PS&E Received 08/27/2004
    Right of Way
    Certification Issued 09/15/2004
    Traffic
    25% Design Review 25% Plans Approved 05/10/2004
    100% Design Review 100% Plans Received 05/19/2004
    100% Design Review 100% Plans Approved 08/20/2004
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating