Project Description:
CANTON- ROADWAY RECONSTRUCTION INCLUDING SIGNALS ON A SECTION OF ROUTE 138 (WASHINGTON STREET)
Location:
  • Town of Canton
  • Construction Begins: Autumn 1999
    Construction Ends: Spring 2001
    Resident Engineer: Brian McKenney
    Construction Contract Value: $1,664,009.45
    Construction Bid Price: $1,422,809.45
    Initial Construction Estimate: $1,476,780.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 30102 -- Construction Contract
    RTE 138 (WASHINGTON ST) RECON 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/13/1999
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/06/1998
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 08/28/1999
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Regular Design Exception Approved 08/17/1998
    Environmental
    ITS
    Utilities
    Non Participating