Project Description:
EASTHAMPTON- INTERSECTION IMPROVEMENTS @ POMEROY MEADOW ROAD, LOUDVILLE ROAD, GLENDALE STREET, WEST STREET (0.62 MILE)
This project begins on Pomeroy Meadow Road in Easthampton and extends in a northeasterly direction along Pomeroy Meadow Road, crossing the intersection of Glendale Road and Loudville Road, and continuing along West Street. This project also includes a portion of Loudville Road in a generally southeasterly direction. There will improvements to alignments, roadway sight distance and grading with a minimal impact to driveways for existing homes in the area.
Location:
  • Town of Easthampton
  • Construction Begins: Autumn 2013
    Construction Ends: Spring 2015
    Resident Engineer: Victoria Strainge
    Construction Contract Value: $2,568,680.00
    Construction Bid Price: $2,576,952.50
    Initial Construction Estimate: $2,719,656.50
    MassHighway District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77971 -- Construction Contract
    Roadway Reconstruction and Related Work at the Intersection of Pomeroy Meadow and Loudville Roads and Glendale and West Streets. 51% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/17/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/02/1997
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 11/28/2005
    Project Status Advertised 06/22/2013
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 09/15/2005
    Design
    Highway Design Process 25% Plans Received 07/04/2006
    Highway Design Process 25% Comments to DE 04/03/2008
    Highway Design Process 25% Comments to DE 10/10/2008
    Highway Design Process Design Public Hearing 03/11/2009
    75% Design 75% Plans Received 02/17/2010
    75% Design 75% Comments to DE 03/03/2010
    100% Design 100% Plans Received 01/11/2013
    100% Design 100% Comments to DE 02/25/2013
    Final Design PS&E to FAPO 06/19/2013
    Final Design PS&E Received 05/24/2013
    Right of Way
    Certification Issued 06/19/2013
    Plans Requested 03/11/2010
    Plans Received 03/01/2010
    Plans Received 08/31/2012
    Plans Received 10/05/2012
    Plans Received 11/29/2012
    Plans Received 02/25/2013
    Plans Reviewed 03/11/2010
    Plans Comments to DE 07/10/2012
    Plans Comments to DE 10/21/2012
    Plans Revised 04/26/2012
    Plans Revised 03/14/2013
    Requirements Requirements 09/29/2006
    Requirements Requirements 11/26/2012
    Traffic
    25% Design Review 25% Plans Received 07/21/2006
    25% Design Review 25% Plans Approved 12/13/2006
    75% Traffic Plans 75% Plans Approved 07/13/2010
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 10/22/2012
    Section 404 (ACOE) Permit Issued 02/04/2013
    ITS
    Utilities
    Non Participating