Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRAINTREE- RECONSTRUCTION OF UNION STREET, FROM ROUTE 3 ROTARY TO COMMERCIAL STREET
This project consists of the reconstruction of Union Street between Cleveland and Liberty Streets for a distance of approximately 0.98 miles. The project includes pavement reconstruction; intersection improvements at Middle Street including a new traffic signal system, sidewalk and wheelchair ramp installation; and associated resetting and installation of curbs, minor drainage improvements, signs, and pavement markings.
Location:
  • Town of Braintree
  • Construction Begins: Autumn 2010
    Construction Ends: Autumn 2011
    Resident Engineer: Gene Lee
    Construction Contract Value: $3,056,556.00
    Construction Bid Price: $2,685,360.50
    Initial Construction Estimate: $3,897,690.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 66087 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Union Street. (ARRA Project) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/30/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/24/1998
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 08/07/2010
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 09/23/2003
    Highway Design Process 25% Plans Received 01/17/2006
    Highway Design Process 25% Plans Rejected 10/14/2003
    Highway Design Process 25% Comments to DE 07/14/2006
    Highway Design Process Design Public Hearing 11/30/2006
    75% Design 75% Plans Received 06/04/2007
    75% Design 75% Comments to DE 09/18/2007
    Final Design PS&E to FAPO 08/04/2010
    Final Design PS&E Received 07/06/2010
    Subsurface Exploration 100% Plans Received 02/27/2009
    Subsurface Exploration 100% Comments to DE 04/21/2010
    Right of Way
    Certification Issued 07/07/2010
    Plans Reviewed 05/21/2009
    Traffic
    25% Design Review 25% Plans Received 01/19/2006
    25% Design Review 25% Plans Approved 03/07/2006
    75% Design Review 75% Plans Received 06/05/2007
    75% Design Review 75% Plans Approved 06/19/2007
    75% Traffic Plans 75% Plans Received 06/05/2007
    75% Traffic Plans 75% Plans Approved 06/19/2007
    75% Draft Temp Signal 75% Plans Received 06/05/2007
    75% Draft Temp Signal 75% Plans Approved 06/19/2007
    100% Traffic Plans 100% Plans Received 04/23/2009
    100% Traffic Plans 100% Plans Approved 05/19/2009
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating