| Project Description: |
BRAINTREE- RECONSTRUCTION OF UNION STREET, FROM ROUTE 3 ROTARY TO COMMERCIAL STREET
This project consists of the reconstruction of Union Street between Cleveland and Liberty Streets for a distance of approximately 0.98 miles. The project includes pavement reconstruction; intersection improvements at Middle Street including a new traffic signal system, sidewalk and wheelchair ramp installation; and associated resetting and installation of curbs, minor drainage improvements, signs, and pavement markings.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Autumn 2010 |
| Project Manager: | Jocelyn Dewire![]() |
| Estimated Construction Cost: | $4,808,810.00 |
| Funding Provision: | This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| MassHighway District: | District 4 |
| Current Status: | Final Plans, Specifications and Estimate have been forwarded to the Capital Expenditure Program Office (as of 08/04/2010) |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||