BRAINTREE- RECONSTRUCTION OF UNION STREET, FROM ROUTE 3 ROTARY TO COMMERCIAL STREET
This project consists of the reconstruction of Union Street between Cleveland and Liberty Streets for a distance of approximately 0.98 miles. The project includes pavement reconstruction; intersection improvements at Middle Street including a new traffic signal system, sidewalk and wheelchair ramp installation; and associated resetting and installation of curbs, minor drainage improvements, signs, and pavement markings.
Location:
  • Town of Braintree
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2010
    Project Manager: Jocelyn Dewire
    Estimated Construction Cost: $4,808,810.00
    Funding Provision: This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    MassHighway District: District 4
    Current Status: Final Plans, Specifications and Estimate have been forwarded to the Capital Expenditure Program Office (as of 08/04/2010)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2010
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BRAINTREE
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category American Recovery & Reinvestment Act
    Federal Cost: $5,553,856.00
    State Cost: $0.00
    Total Cost: $5,553,856.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/24/1998
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 09/23/2003
    Highway Design Process 25% Plans Received 01/17/2006
    Highway Design Process 25% Plans Rejected 10/14/2003
    Highway Design Process 25% Comments to DE 07/14/2006
    Highway Design Process Design Public Hearing 11/30/2006
    75% Design 75% Plans Received 06/04/2007
    75% Design 75% Comments to DE 09/18/2007
    100% Design 100% Plans Received 02/27/2009
    100% Design 100% Comments to DE 04/21/2010
    Final Design PS&E to CEPO 08/04/2010
    Final Design PS&E Received 07/06/2010
    Right of Way
    Certification Issued 07/07/2010
    Plans Reviewed 05/21/2009
    Traffic
    25% Design Review 25% Plans Received 01/19/2006
    25% Design Review 25% Plans Approved 03/07/2006
    75% Design Review 75% Plans Received 06/05/2007
    75% Design Review 75% Plans Approved 06/19/2007
    75% Traffic Plans 75% Plans Received 06/05/2007
    75% Traffic Plans 75% Plans Approved 06/19/2007
    75% Draft Temp Signal 75% Plans Received 06/05/2007
    75% Draft Temp Signal 75% Plans Approved 06/19/2007
    100% Traffic Plans 100% Plans Received 04/23/2009
    100% Traffic Plans 100% Plans Approved 05/19/2009
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating