Project Description:
MILTON- SIGNALS & INTERSECTION IMPROVEMENTS @ BLUE HILL AVENUE (ROUTE 138) & NEPONSET VALLEY PARKWAY
This major safety improvement project will enhance safety and improve efficiency by installing a new traffic signal at the intersection of Blue Hill Avenue (Route 138) and Neponset Valley Parkway. There will also be major geometric improvements at this intersection, such as road widening and improved lane alignment and configurations to improve sight distance. This work will include a new retaining wall and the extension of an existing culvert, resulting in some significant drainage improvements. New signs and pavement markings will also be installed.
Location:
  • Town of Milton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2014
    Project Manager: Brian Chapman
    Estimated Construction Cost: $460,000.00
    MassHighway District: District 4
    Current Status: Comments on the 25% design phase project plans have been returned to the Design Engineer. (as of 05/22/2006)

    Contracts (2) Progress
    # 33135 -- Design -- Traffic Signing/Signals
    Statewide - provide traffic engineering services in connection with traffic signal improvement projects at State Highway Locations. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/07/1998
    Project Review Committee PRC Approved 07/20/1998
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 01/15/2004
    Consultant Contract Process NTP Issued 02/25/2004
    Design
    Highway Design Process 25% Plans Received 06/30/2005
    Highway Design Process 25% Comments to DE 05/22/2006
    Highway Design Process Design Public Hearing 06/16/2009
    Right of Way
    Plans Received 12/23/2005
    Requirements Requirements 12/27/2005
    Traffic
    25% Design Review 25% Plans Received 06/30/2005
    25% Design Review 25% Plans Approved 07/13/2005
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating