Project Description:
CANTON- IMPROVEMENTS & SIGNALIZATION, ROUTE 138 (TURNPIKE STREET) AT WASHINGTON STREET AND ROUTE 138 AT RANDOLPH STREET
The roadway improvements proposed in this project are associated in part with the construction of Reebok world Headquarters. As part of the approval process for this development, traffic signal and geometric improvements to the roadway are required at the intersection of Route 138 at Washington and Randolph Streets. Also included in this project are roadway widening, new sidewalks, bicycle accommodations, traffic signal modifications, improved pavement markings and signing, drainage system modifications and retaining wall construction.
Location:
  • Town of Canton
  • Construction Begins: Winter 2005/2006
    Construction Ends: Spring 2009
    Resident Engineer: Phuong Tran
    Construction Contract Value: $2,990,581.75
    Construction Bid Price: $2,195,064.50
    Initial Construction Estimate: $1,623,182.75
    MassHighway District: District 4
    Current Status: This project is substantially complete. With only minor punch list items remaining. (as of 11/13/2009)

    Contracts (1) Progress
    # 43286 -- Construction Contract
    Canton - Roadway Reconstruction at the Intersections of Route 138 (Turnpike Street) at Washington Street and Route 138 (Turnpike Street) at Randolph Street 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/24/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is substantially complete. With only minor punch list items remaining.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/14/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Status Advertised 06/11/2005
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 01/01/2002
    Highway Design Process 25% Plans Approved 10/07/2003
    Highway Design Process 25% Comments to DE 10/08/2003
    Highway Design Process Design Public Hearing 11/24/2003
    75% Design 75% Plans Received 08/31/2004
    75% Design 75% Comments to DE 12/31/2004
    100% Design 100% Plans Received 02/14/2005
    100% Design 100% Comments to DE 05/17/2005
    Final Design PS&E to CEPO 06/07/2005
    Final Design PS&E Received 06/07/2005
    Right of Way
    Certification Issued 05/18/2005
    Plans Received 09/14/2004
    Plans Accepted 09/14/2004
    Traffic
    25% Design Review 25% Plans Approved 10/07/2003
    75% Design Review 75% Plans Received 09/02/2004
    75% Design Review 75% Plans Approved 10/27/2004
    75% Traffic Plans 75% Plans Received 09/02/2004
    75% Traffic Plans 75% Plans Approved 09/08/2004
    75% Draft Temp Signal 75% Plans Received 09/02/2004
    75% Draft Temp Signal 75% Plans Approved 10/20/2004
    75% TMP 75% Plans Received 09/02/2004
    75% TCA 75% Plans Received 09/02/2004
    75% TCA 75% Plans Approved 10/27/2004
    100% Design Review 100% Plans Received 02/15/2005
    100% Design Review 100% Plans Approved 03/24/2005
    100% Traffic Plans 100% Plans Received 02/15/2005
    100% Traffic Plans 100% Plans Approved 03/24/2005
    100% Temp Signal 100% Plans Received 02/15/2005
    100% Temp Signal 100% Plans Approved 03/24/2005
    100% TCA 100% Plans Received 02/18/2005
    100% TCA 100% Plans Approved 03/22/2005
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating