Project Description:
BOSTON- TRAFFIC SAFETY IMPROVEMENTS INCLUDING SIGNALS ON A SECTION OF DARTMOUTH STREET
The purpose of this project is to reconstruct traffic signal systems for the intersections of Dartmouth Street with Boylston Street and St. James Avenue. New traffic signal equipment and overhead street lighting will be installed along with new concrete sidewalks and wheelchair ramps.
Location:
  • City of Boston
  • Construction Begins: Autumn 2001
    Construction Ends: Spring 2004
    Resident Engineer: Ken Lim
    Construction Contract Value: $5,468,392.38
    Construction Bid Price: $1,968,032.90
    Initial Construction Estimate: $1,824,000.00
    MassHighway District: District 4
    Current Status: Project is complete. (as of 02/25/2005)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/26/2001
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/06/1999
    Project Review Committee PRC Tabled 05/11/1999
    Project Review Committee PRC Denied 04/24/2000
    Project Status Advertised 09/30/2000
    Project Status Advertised 07/21/2001
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities