BOSTON- SEWER AND DRAINAGE IMPROVEMENTS ON SECTIONS OF WINTHROP, MORELAND AND DUDLEY STREETS
Location:
  • City of Boston
  • Construction Begins: Summer 2001
    Construction Ends: Spring 2002
    Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $378,970.00
    Construction Bid Price: $286,970.00
    Initial Construction Estimate: $199,000.00
    MassHighway District: District 4

    Contracts (1) Progress
    # 31342 -- Construction Contract
    WINTHROP MORELAND AND DUDLEY ST SEWER 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/29/2001
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 03/03/2001
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating