Project Description:
MONTAGUE- CONSTRUCTION OF THE FRANKLIN COUNTY BIKEWAY (PHASE I)
The Franklin County Bikeway Phase I project will result in the construction of a new bituminous concrete bikepath to carry bicycle and pedestrian traffic in the Town of Montague. This phase begins at Montague City Road as a shared road facility and continues north onto Depot Street. At Depot Street it connects to an existing abandoned railroad right-of-way and becomes an off-road facility terminating at Unity Park. The total length of this project is approximately 4000 meters.
Location:
  • Town of Montague
  • Construction Begins: Spring 2004
    Construction Ends: Spring 2008
    Resident Engineer: John Burek
    Construction Contract Value: $1,524,876.38
    Construction Bid Price: $1,355,396.17
    Initial Construction Estimate: $1,426,980.00
    MassHighway District: District 2
    Current Status: Bike path under construction (as of 07/14/2004)
    Additional Info: Work suspended until Spring 2008 (as of 11/14/2007)

    Contracts (1) Progress
    # 34566 -- Construction Contract
    Construction of the Franklin County Bikeway - Phase I. 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/02/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bike path under construction
    Additional Info
    Work suspended until Spring 2008
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/03/1999
    Project Review Committee PRC Approved 05/24/1999
    Project Status Advertised 08/23/2003
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 04/16/1999
    Highway Design Process Design Public Hearing 06/15/2000
    Distribution of Plans 100% Plans Received 03/26/2002
    Distribution of Plans 100% Comments to DE 05/13/2002
    Geotechnical PS&E to FAPO 08/06/2003
    Geotechnical PS&E Received 12/18/2002
    Right of Way
    Certification - Municipality Issued - All necessary ROW acquired 07/29/2003