Project Description:
CONCORD- LINCOLN- LIMITED ACCESS HIGHWAY IMPROVEMENTS AT ROUTE 2 & 2A, BETWEEN CROSBY'S CORNER & BEDFORD ROAD, INCLUDES C-19-024
The purpose of this project is to provide safety improvements at Crosby’s Corner (intersection of Route 2, Cambridge Turnpike and Route 2A/ the Concord Turnpike). This will be accomplished by constructing neighborhood service roads which will be parallel to Route 2. This will also be accomplished by constructing a bridge to carry Route 2 over the other routes. The benefits of the project include the ability to safely and efficiently accommodate traffic and to provide safe access to the residences and businesses located along the project corridor. The project starts at the Bedford Road intersection in the Town of Lincoln and extends to 300 feet west of Sandy Pond Road in the Town of Concord.
Location:
  • Town of Concord
  • Town of Lincoln
  • Construction Begins: Spring 2012
    Construction Ends: Summer 2016
    Resident Engineer: Brian Polley
    Construction Contract Value: $48,160,546.00
    Construction Bid Price: $42,228,757.00
    Initial Construction Estimate: $51,828,136.00
    Total Estimated Project Cost: $65,000,000.00
    MassHighway District: District 4
    Current Status: Excavating and forming footing for retaining wall between Old Cambridge Turnpike and "The Commons". (as of 11/21/2014)

    Contracts (13) Progress
    # 32147 -- Design -- Hwy Eng Open End
    Statewide - Provide engineering design and review services to the Highway Engineering Division on an open end basis for highway and bridge projects. Final
    # 34533 -- Design -- Bridge Rehab/Recon/New Const
    Concord/Lincoln - Final Design Services to complete the project from the 25% Design Stage to the PSE/Advertising stage, including construction phase services for the diamond i Final
    # 41489 -- Design -- Geotechnical
    Statewide - implement geophysical methods on statewide designed and constructed bridge and highway projects. Final
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 56771 -- Design -- MEPA/NEPA Compliance
    Work will be assigned on an as-needed basis including Early Environmental Coordination and Public Outreach including Federal and State Agency coordination. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64322 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 71104 -- Construction Contract
    Roadway Reconstruction and Related Work (Including 1 Bridge and 14 Retaining Walls) along a Section of Route 2 (Crosbys Corner Interchange). 58% Complete
    # 94420 -- Design -- MEPA/NEPA Compliance
    CROSBY'S CORNER, RTE 2, ENVIRO Final
    # 99191 -- Design -- MEPA/NEPA Compliance
    Route 2/ Crosby's Corner FEIR/ EA Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/11/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Excavating and forming footing for retaining wall between Old Cambridge Turnpike and "The Commons".
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/19/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/17/2011
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 10/04/2004
    Consultant Contract Process NTP Issued 03/15/2005
    Design
    Highway Design Process 25% Plans Received 05/15/2002
    Highway Design Process 25% Plans Approved 05/20/2004
    Highway Design Process 25% Comments to DE 03/23/2005
    Highway Design Process Design Public Hearing 05/13/2003
    75% Design 75% Plans Received 01/21/2011
    75% Design 75% Plans Rejected 11/07/2008
    75% Design 75% Comments to DE 03/31/2011
    Final Design PS&E to FAPO 09/12/2011
    Final Design PS&E Received 09/09/2011
    Subsurface Exploration 100% Plans Received 07/15/2011
    Subsurface Exploration 100% Comments to DE 08/15/2011
    Right of Way
    Certification - MassDOT Issued - All necessary ROW acquired 09/15/2011
    Plans Received 09/21/2011
    Plans Comments to DE 02/24/2012
    Requirements Requirements 06/27/2011
    Advanced Title Exam Requested 05/11/2011
    Advanced Title Exam Completed 08/17/2011
    Registry Plans/Instruments Requested 05/13/2011
    Registry Plans/Instruments Comments to DE 06/10/2009
    Traffic
    75% Traffic Plans 75% Plans Received 02/16/2011
    75% Traffic Plans 75% Plans Approved 02/22/2011
    75% Draft Temp Signal 75% Plans Received 06/06/2008
    75% TMP 75% Plans Approved 04/12/2011
    100% Traffic Plans 100% Plans Received 07/19/2011
    100% Traffic Plans 100% Plans Approved 07/22/2011
    100% TMP 100% Plans Approved 08/12/2011
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 04/07/2010
    Wetlands Protection Act Permit Expires 04/07/2013
    Section 404 (ACOE) Permit Issued 09/15/2011
    Section 404 (ACOE) Permit Expires 09/30/2016
    Section 401 (WQC) Permit Issued 08/05/2011
    Section 401 (WQC) Permit Expires 08/05/2016
    ITS
    Utilities