Project Description:
NEWBURY- BRIDGE REPLACEMENT, N-10-010, ROUTE 1A (HIGH ROAD) OVER THE PARKER RIVER
The proposed project will replace the existing bridge in its present location with improvements to the approach roadway. The original design entailed providing one lane of traffic in each direction and a sidewalk during the construction. Based on additional deterioration discovered when the project first commenced, the design was modified to utilize single stage construction with the bridge being closed and all traffic detoured. The formal, signed detour route utilizes Route 133, Route 1 and Hanover Street.
Location:
  • Town of Newbury
  • Construction Begins: Autumn 2006
    Resident Engineer: Jeffery Lavallee
    Construction Contract Value: $14,125,670.00
    Construction Bid Price: $12,742,418.00
    Initial Construction Estimate: $8,576,635.00
    MassHighway District: District 4
    Current Status: This project is substansially complete. Final inspection has been held. All punch list items have been addressed. (as of 01/26/2010)

    Contracts (3) Progress
    # 30142 -- Design -- Bridge Rehab/Recon/New Const
    Newbury - Route 1A (High Road) over Parker River BR#N-10-010. Preliminary/ Final Design. Final
    # 49211 -- Construction Contract
    Newbury - Bridge Replacement (N-10-010) (Concrete) - Route 1 A (High Road) over the Parker River 100% Complete
    # 96043 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON A Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/17/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Bridge Repl/Rehab
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is substansially complete. Final inspection has been held. All punch list items have been addressed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 11/09/1999
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 09/10/2005
    Project Status Advertised 11/26/2005
    Project Status Advertised 09/09/2006
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 04/27/2001
    Highway Design Process 25% Comments to DE 05/19/2001
    Highway Design Process Design Public Hearing 11/15/2001
    75% Design 75% Plans Received 11/16/2001
    75% Design 75% Comments to DE 03/12/2002
    25% 100% Plans Received 09/12/2002
    25% 100% Comments to DE 03/28/2003
    25% 100% Plans Complete 06/18/2003
    Final Design PS&E to CEPO 05/12/2005
    Final Design PS&E Received 04/11/2005
    Right of Way
    Requirements Requirements 02/04/2002
    Traffic
    Design Exceptions
    Environmental
    Section 401 (WQC) Permit Issued 11/16/2005
    Coastal Zone Management Permit Issued 08/16/2006
    Coast Guard Permit Issued 08/11/2006
    ITS
    Utilities
    Non Participating