Project Description:
DEDHAM- 128 ADD-A-LANE BRIDGES (BRIDGE III), ROUTE 1 & 1A OVER ROUTE I-95/128, D-05-027, D-05-046, D-05-044, D-05-045
This contract includes the widening of approximately 1.36 miles of I-95 (Route 128) and the replacement of the Route 1 and 1A Bridges over I-95 in the Towns of Dedham and Westwood. The widening, which will include a 12-foot travel lane and 10-foot shoulder toward the median, will extend between the MBTA Franklin Commuter Rail Bridge located just south of the Route 1 bridge structures and extending north to the high point of the roadway between the Route 1A and Route 109 bridge structures. The proposed Route 1 structure will consist of a two-span steel superstructure. The proposed Route 1A bridges will both be single span steel structures each with a span length of approximately 33.0 meters or 108 feet. A temporary three lane bridge will be constructed over I-95 on the north side of Route 1 to manage the existing traffic during construction. Staged construction will be required for the Route 1A bridges, replacing one half at a time. One travel lane in each direction will be open during the Route 1A bridge replacements. Four noise barrier locations, along with landscaping, will be constructed within this contract, adjacent to the following local roads: Poplar Street, Robinwood Road, Chickering Road and Manning Road. Major drainage improvements will also be installed during this contract.
Location:
  • Town of Dedham
  • Town of Westwood
  • Construction Begins: Summer 2006
    Construction Ends: Autumn 2010
    Resident Engineer: Harry Thompson
    Construction Contract Value: $40,549,811.00
    Construction Bid Price: $36,453,047.00
    Initial Construction Estimate: $25,448,696.00
    MassHighway District: District 4
    Current Status: Roadway widening operations inside the projects median and along I-95 N.B and S.B. low speed travel lanes will continue in August 2010. Paving operations will continue on Rte 1 in August as well. (as of 08/02/2010)

    Contracts (3) Progress
    # 30260 -- Design -- Bridge Rehab/Recon/New Const
    Dedham - Route 1 & 1A over Route 128. BR#s D-5-27 (NB), D-5-46 (SB), D-5-44 (NB), D-5-45 (SB) Final
    # 45533 -- Construction Contract
    Dedham - Roadway Reconstruction Including 4 Bridges (Steel) at the Interstate 95 (Rte 128) & Rte 1 & 1A Interchange 83% Complete
    # 57732 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects, includes ABP projects Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/24/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Bridge Repl/Rehab
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Roadway widening operations inside the projects median and along I-95 N.B and S.B. low speed travel lanes will continue in August 2010. Paving operations will continue on Rte 1 in August as well.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/15/2000
    Project Review Committee Received 03/23/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 09/24/2005
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 01/03/2002
    Design
    Highway Design Process 25% Plans Received 05/30/2003
    Highway Design Process 25% Comments to DE 12/22/2003
    Highway Design Process 25% Plans Complete 08/13/2004
    Highway Design Process Design Public Hearing 09/23/2004
    25% 75% Plans Received 02/01/2005
    25% 75% Comments to DE 05/13/2005
    75% 100% Plans Received 08/25/2005
    75% 100% Comments to DE 10/14/2005
    Subsurface Exploration PS&E to CEPO 08/29/2005
    Subsurface Exploration PS&E Received 08/25/2005
    Right of Way
    Certification Issued 09/16/2005
    Plans Requested 10/28/2004
    Plans Received 12/16/2004
    Plans Accepted 01/28/2005
    Registry Plans/Instruments Received 08/21/2005
    Traffic
    25% Design Review 25% Plans Received 06/24/2003
    25% Design Review 25% Plans Approved 08/13/2004
    75% Design Review 75% Plans Received 02/10/2005
    75% Design Review 75% Plans Approved 04/20/2005
    75% Traffic Plans 75% Plans Received 02/10/2005
    75% Traffic Plans 75% Plans Approved 04/20/2005
    75% TMP 75% Plans Received 02/10/2005
    75% TMP 75% Plans Approved 04/20/2005
    100% Design Review 100% Plans Received 08/29/2005
    100% Design Review 100% Plans Approved 09/26/2005
    100% Traffic Plans 100% Plans Received 08/29/2005
    100% Traffic Plans 100% Plans Approved 09/26/2005
    100% TMP 100% Plans Received 08/29/2005
    100% TMP 100% Plans Approved 09/26/2005
    Design Exceptions
    Regular Design Exception Approved 08/13/2004
    Regular Design Exception Submitted 03/30/2004
    Environmental
    ITS
    Utilities
    Non Participating