Project Description:
DEDHAM- NEEDHAM- BRIDGE REPLACEMENT ON ROUTE 128 (ADD-A-LANE BRIDGES) D-05-042, D-05-043, D-05-040, D-05-041, D-05-038=N-04-030, D-05-039, N-04-029 (BRIDGE IV)
The work consists of the replacement of the Route 109, 135, Charles River, and Great Plain Avenue bridges. The roadway work will consist of adding a new 12-foot travel lane and 10-foot shoulder toward the median in both directions. The limits will begin from just south of Route 109 structures in Dedham and extend to just north of the Needham railroad line in Needham. The total length of project is approximately 4.0 miles of I-95/Route 128 roadway. A noise barrier will be constructed along Roberts Road. The work will also include retaining wall construction and drainage improvements addressing the latest stormwater management standards.
Location:
  • Town of Dedham
  • Town of Needham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Winter 2009/2010
    Project Manager: Lawrence Cash
    Estimated Construction Cost: $105,900,164.00
    Funding Provision: This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    MassHighway District: District 4
    Current Status: This project has been advertised for construction bids. (as of 09/19/2009)

    Contracts (2) Progress
    # 31181 -- Design -- Bridge Rehab/Recon/New Const
    Dedham, Needham - Routes 109 & 135, & Charles River Bridges Route 128 Add-a-Lane Bridges (Bridge IV) Final
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2010
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: DEDHAM
    NEEDHAM
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

  • A/C amount
  • per Dave Flint's e-mail of 11/16/09 (AM), all BR funds are now to be NHS funds
  • Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $12,400,000.00
    State Cost: $3,100,000.00
    Total Cost: $15,500,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $9,600,000.00
    State Cost: $2,400,000.00
    Total Cost: $12,000,000.00

    Planned Federal FY: 2011
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: DEDHAM
    NEEDHAM
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

  • A/C amount
  • Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $9,600,000.00
    State Cost: $2,400,000.00
    Total Cost: $12,000,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $3,600,000.00
    State Cost: $900,000.00
    Total Cost: $4,500,000.00

    Planned Federal FY: 2012
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: DEDHAM
    NEEDHAM
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

  • A/C amount
  • Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $8,000,000.00
    State Cost: $2,000,000.00
    Total Cost: $10,000,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $9,600,000.00
    State Cost: $2,400,000.00
    Total Cost: $12,000,000.00

    Planned Federal FY: 2013
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: DEDHAM
    NEEDHAM
    Category: Advertised Projects Constr.
    Budget Section: 1C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $8,000,000.00
    State Cost: $2,000,000.00
    Total Cost: $10,000,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $9,600,000.00
    State Cost: $2,400,000.00
    Total Cost: $12,000,000.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/17/2000
    Project Review Committee Received 05/23/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Status Advertised 09/19/2009
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 09/18/2001
    Consultant Contract Process Workhours Approved 12/31/2002
    Consultant Contract Process NTP Issued 07/31/2003
    Design
    Highway Design Process 25% Plans Received 01/07/2005
    Highway Design Process 25% Comments to DE 08/01/2005
    Highway Design Process Design Public Hearing 09/21/2005
    25% 75% Plans Received 03/03/2006
    25% 75% Plans Received 09/12/2008
    25% 75% Comments to DE 12/04/2008
    75% 100% Plans Received 06/03/2009
    75% 100% Comments to DE 09/02/2009
    Subsurface Exploration PS&E to CEPO 09/04/2009
    Subsurface Exploration PS&E to CEPO 09/10/2009
    Subsurface Exploration PS&E Received 09/04/2009
    Subsurface Exploration PS&E Received 10/30/2009
    Right of Way
    Plans Received 01/15/2005
    Traffic
    25% Design Review 25% Plans Received 03/02/2005
    25% Design Review 25% Plans Approved 03/16/2005
    75% Design Review 75% Plans Received 03/15/2006
    75% Traffic Plans 75% Plans Received 09/23/2008
    75% Draft Temp Signal 75% Plans Received 03/15/2006
    75% TMP 75% Plans Received 12/04/2009
    75% TMP 75% Plans Approved 12/11/2009
    100% Traffic Plans 100% Plans Received 06/10/2009
    100% Traffic Plans 100% Plans Approved 07/21/2009
    Design Exceptions
    Regular Design Exception Approved 01/17/2006
    Regular Design Exception Submitted 03/08/2005
    Environmental
    Wetlands Protection Act Permit Issued 06/19/2009
    Wetlands Protection Act Permit Expires 06/19/2012
    Section 404 (ACOE) Permit Issued 09/18/2009
    Section 404 (ACOE) Permit Expires 01/20/2010
    Section 401 (WQC) Permit Issued 09/15/2009
    Chapter 91 Permit Issued 09/10/2009
    ITS
    Utilities
    Non Participating