| Project Description:
|
BOSTON- ROADWAY RECONSTRUCTION INCLUDING SIGNALS AT 12 LOCATIONS
|
| Location:
|
City of Boston
|
| Construction Begins:
|
Winter 2000/2001 |
| Construction Ends:
|
Spring 2004 |
| Resident Engineer:
|
Ahmad Ilyas |
| Construction Contract Value:
|
$2,058,363.70 |
| Construction Bid Price:
|
$1,788,163.70 |
| Initial Construction Estimate:
|
$1,344,000.00 |
| MassHighway District:
|
District 4 |
| Current Status:
|
Completion of island reconstruction at Hancock Street/ Columbia Road. Completion of proposed island, signal equipment installation, Intersection resurfaced with Modified Top, placement of thermo plastic traffic lines and crosswalks and ongoing final inspections at all 12 intersections. (as of 02/25/2005) |
| Additional Info:
|
Completion/ Acceptance delayed due to extra work order at Hancock Street and Columbia Road.Boston Traffic Department conducting final inspections with limited manpower. (as of 02/25/2005) |