BOSTON- TRAFFIC SIGNAL AND SAFETY IMPROVEMENTS, ROUTE I-93 RAMPS AT COLUMBIA ROAD
Location:
  • City of Boston
  • Construction Begins: Winter 2002/2003
    Construction Ends: Autumn 2004
    Resident Engineer: John Lepore
    Construction Contract Value: $677,506.00
    Construction Bid Price: $569,551.30
    Initial Construction Estimate: $404,000.00
    MassHighway District: District 4
    Current Status: Project is complete with the exception of the punch list and final Inspection. (as of 04/28/2005)

    Contracts (2) Progress
    # 30203 -- Design -- Traffic Signing/Signals
    Statewide - Traffic engineering services with traffic signal improvement projects. Final
    # 33192 -- Construction Contract
    Traffic Signals and Safety Improvements at I-93 Ramps and Columbia Road 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2003
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete with the exception of the punch list and final Inspection.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/27/2001
    Project Review Committee Received 03/30/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/26/2001
    Project Status Advertised 09/14/2002
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating