| Project Description: |
BOSTON- TRAFFIC SIGNAL AND SAFETY IMPROVEMENTS, ROUTE I-93 RAMPS AT COLUMBIA ROAD
|
| Location: |
|
| Construction Begins: | Winter 2002/2003 |
| Construction Ends: | Autumn 2004 |
| Resident Engineer: | John Lepore![]() |
| Construction Contract Value: | $677,506.00 |
| Construction Bid Price: | $569,551.30 |
| Initial Construction Estimate: | $404,000.00 |
| MassHighway District: | District 4 |
| Current Status: | Project is complete with the exception of the punch list and final Inspection. (as of 04/28/2005) |
|