| Project Description: |
DEERFIELD- BRIDGE REHABILITATION, D-06-044 & D-06-045, ROUTE I-91 (NB & SB) OVER THE DEERFIELD RIVER (STILLWATER ROAD AND LOWER ROAD)
The work included in this project involves the replacement of the existing bridge structures carrying I-91 northbound and southbound over the Deerfield River, Stillwater Road and Lower Road. The northbound bridges will be constructed first within the existing median, and will be used to carry the southbound traffic during construction of the southbound bridges.
|
| Location: |
|
| Construction Begins: | Spring 2012 |
| Construction Ends: | Spring 2016 |
| Resident Engineer: | Michael Los![]() |
| Construction Contract Value: | $40,229,983.00 |
| Construction Bid Price: | $36,204,975.90 |
| Initial Construction Estimate: | $42,004,486.29 |
| MassHighway District: | District 2 |
|