Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRAINTREE- DE-ICING STORAGE BUILDING & RELATED WORK
CONSTRUCTION OF A CHEMICAL ( SALT ) STORAGE BUILDING AND RELATED WORK.
Location:
  • Town of Braintree
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassHighway
    Construction Begins: Winter 2010/2011
    Project Manager: Thomas P Conneely
    Estimated Construction Cost: $500,000.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/14/2001
    Project Review Committee Received 08/14/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 01/07/2002
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating