DEDHAM- BRIDGE REHABILITATION, D-05-005, AMES STREET OVER THE CHARLES RIVER
The proposed project consists of replacing the currently closed easterly sidewalk spans (built 1917) with a new replicated structure. The original masonry arches (built 1870) and concrete arches (built 1926) along the westerly side will be maintained and a new deck will span these historic arches. The bridge will be opened to vehicle traffic during construction and a foot-bridge will be constructed for pedestrians.
Location:
  • Town of Dedham
  • Construction Begins: Winter 2008/2009
    Construction Ends: Summer 2012
    Resident Engineer: Eric Zilinsky
    Construction Contract Value: $8,783,582.00
    Construction Bid Price: $7,647,620.00
    Initial Construction Estimate: $6,501,180.00
    MassHighway District: District 4
    Current Status: Drilling of concrete micropiles for the new bridge structure is in progress. This work will continue in to August 2010. (as of 08/02/2010)

    Contracts (4) Progress
    # 31221 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 2 Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57419 -- Construction Contract
    Dedham- Bridge Replacement (D-05-005), Ames Street over the Charles River 56% Complete
    # 97043 -- Design -- Bridge Open End
    Rd2 Brd FA NHS/NON-NHS CONT. A Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REHABILITATION
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Drilling of concrete micropiles for the new bridge structure is in progress. This work will continue in to August 2010.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/25/2001
    Project Review Committee Received 11/05/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 09/13/2008
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 06/12/2004
    Design
    Highway Design Process 25% Plans Received 10/06/2003
    Highway Design Process 25% Comments to DE 06/27/2004
    Highway Design Process Design Public Hearing 03/09/2004
    75% Design 75% Plans Received 10/01/2004
    75% Design 75% Comments to DE 06/15/2005
    25% 100% Plans Received 11/03/2005
    25% 100% Comments to DE 03/03/2006
    Final Design PS&E to CEPO 09/09/2008
    Final Design PS&E Received 09/15/2006
    Right of Way
    Certification Issued 05/30/2006
    Plans Received 04/29/2004
    Requirements Requirements 10/29/2004
    Traffic
    25% Design Review 25% Plans Approved 04/14/2004
    75% Design Review 75% Plans Received 10/05/2004
    75% Design Review 75% Plans Approved 06/10/2005
    75% Traffic Plans 75% Plans Received 10/05/2004
    75% Traffic Plans 75% Plans Approved 06/10/2005
    100% Design Review 100% Plans Received 01/09/2006
    100% Design Review 100% Plans Approved 02/27/2006
    100% Traffic Plans 100% Plans Received 09/02/2008
    100% Traffic Plans 100% Plans Approved 09/05/2008
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 07/12/2005
    Section 401 (WQC) Permit Issued 07/26/2005
    ITS
    Utilities
    Non Participating