Project Description:
NEEDHAM- WELLESLEY- BRIDGE REHAB/REPLACEMENT ON I-95/ROUTE 128 (ADD-A-LANE - 3.25 MILES); INCLUDES 5 BRIDGES (BRIDGE V CONTRACT)
This project is the final bridge contract (Bridge V) for the I-95/93 (Route 128) Transportation Improvement Project. The work includes five bridge locations and approximately 3.25 miles of I-95 roadway reconstruction. The roadway work on I-95, from just south of Kendrick Street to just north of Route 9, includes the installation of an additional 12 foot travel lane and 10 foot shoulder in each direction toward the median, along with new collector/distributor roads between Highland Avenue and Kendrick Street. The collector roads will provide safer weaving movements between the interchanges and provide safer traffic movements to and from the adjacent business park. The bridge locations include the following: Kendrick Street over I-95 (Route 128) in Needham; Highland Avenue over I-95 (Route 128) in Needham; MBTA RR (Newton Upper Falls Branch) over I-95 (Route 128) in Needham; I-95 (Route 128) over Central Street in Needham; and, I-95 (Route 128) over Route 9 in Wellesley.
Location:
  • Town of Needham
  • Town of Wellesley
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2012
    Project Manager: Lawrence Cash
    Estimated Construction Cost: $126,872,310.00
    Funding Provision: This project is planned to be funded through the 2012 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    MassHighway District: District 4
    Current Status: Comments on the 25% design phase project plans have been returned to the Design Engineer. (as of 08/07/2009)

    Contracts (1) Progress
    # 34072 -- Design -- Bridge Rehab/Recon/New Const
    Needham/Wellesley - Design for the replacement/rehabilitation of bridges under the final bridge contract of the I-95/93 Route 128 Transportation Improvement Project. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2012
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NEEDHAM
    WELLESLEY
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • A/C amount
  • Category BRR ON SYSTEM
    Federal Cost: $4,000,000.00
    State Cost: $1,000,000.00
    Total Cost: $5,000,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $9,600,000.00
    State Cost: $2,400,000.00
    Total Cost: $12,000,000.00

    Planned Federal FY: 2013
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NEEDHAM
    WELLESLEY
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • A/C amount
  • Category BRR ON SYSTEM
    Federal Cost: $8,000,000.00
    State Cost: $2,000,000.00
    Total Cost: $10,000,000.00
    Category NATIONAL HIGHWAY SYSTEM
    Federal Cost: $12,000,000.00
    State Cost: $3,000,000.00
    Total Cost: $15,000,000.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/26/2002
    Project Review Committee Received 07/29/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/25/2002
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 03/21/2005
    Consultant Contract Process Workhours Approved 02/06/2006
    Consultant Contract Process NTP Issued 10/13/2006
    Design
    Highway Design Process 25% Plans Received 12/11/2008
    Highway Design Process 25% Comments to DE 08/07/2009
    Right of Way
    Plans Received 12/29/2008
    Requirements Requirements 12/29/2008
    Traffic
    25% Design Review 25% Plans Received 05/26/2010
    25% Design Review 25% Plans Approved 06/18/2010
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 12/05/2008
    Wetlands Protection Act Permit Expires 12/05/2011
    ITS
    Utilities
    Non Participating