Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ERVING- GILL- BRIDGE PRESERVATION JOINT REPAIRS, E-10-014=G-04-009, ROUTE 2 OVER THE CONNECTICUT RIVER
Location:
  • Town of Erving
  • Town of Gill
  • Construction Begins: Spring 2008
    Construction Ends: Spring 2010
    Resident Engineer: Sean Burke
    Construction Contract Value: $2,767,943.83
    Construction Bid Price: $2,266,689.00
    Initial Construction Estimate: $1,792,371.30
    MassHighway District: District 2

    Contracts (1) Progress
    # 53414 -- Construction Contract
    Bridge Rehabilitation (E-10-014 = G-04-009) (French King Bridge) - Route 2 (Mohawk Trail) over River Road and the Connecticut River. 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 03/25/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/03/2002
    Project Review Committee Received 09/13/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/18/2002
    Project Status Advertised 02/07/2004
    Project Status Advertised 10/21/2006
    Prj Scope & Negotiation
    Design
    Final Design PS&E to FAPO 09/11/2006
    Final Design PS&E Received 07/25/2006
    Right of Way
    Requirements Requirements 09/12/2006
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating