Project Description:
BOURNE- SAGAMORE ROTARY GRADE SEPARATION PROJECT
As a product of a feasibility study, the current design concept for this area is to grade separate Route 3 and Scenic Highway with a bridge structure located approximately 1,000 feet north of the Sagamore Bridge. Scenic Highway will be relocated to the north, pass under Route 3 north and south and connect into Meeting House Lane. This new alignment will result in a displacement of the “park and ride” lot to the south, and the relocation of the MassHighway Depot, Chamber of Commerce building, and the fire station currently located on the rotary.
Location:
  • Town of Bourne
  • Construction Begins: Autumn 2004
    Construction Ends: Autumn 2008
    Resident Engineer: Michael McGovern
    Construction Contract Value: $37,176,038.74
    Construction Bid Price: $32,770,610.00
    Initial Construction Estimate: $35,610,000.00
    Total Estimated Project Cost: $59,300,000.00
    MassHighway District: District 5

    Contracts (2) Progress
    # 30269 -- Design -- MEPA/NEPA Compliance
    Bourne, Sagamore Rotary Grade Separation Design Environmental EA/EIR Final
    # 36310 -- Construction Contract
    Bourne - Sagamore Rotary Interchange Project 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/08/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/18/2003
    Project Review Committee Received 03/21/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 08/14/2004
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    75% Design Review 75% Plans Approved 04/22/2004
    75% Traffic Plans 75% Plans Approved 04/22/2004
    75% Draft Temp Signal 75% Plans Approved 04/22/2004
    75% TMP 75% Plans Approved 04/22/2004
    100% Design Review 100% Plans Received 09/30/2004
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating