| Project Description: |
CANTON- RECONSTRUCTION ON ROUTE 138, FROM I-93 TO DAN ROAD
This project will reconstruct Route 138 from just south of the I-93 interchange to Dan Road. Route 138 be widened in this area to accommodate standard travel lanes of 12 feet with 8 foot shoulders and sidewalks on both sides of the street.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Winter 2011/2012 |
| Project Manager: | Brian Fallon![]() |
| Estimated Construction Cost: | $2,850,000.00 |
| MassHighway District: | District 4 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||