WELLESLEY- BRIDGE REPLACEMENT, W-13-015, CEDAR STREET OVER ROUTE 9 WORCESTER STREET
The purpose of this project is to replace the superstructure and center pier of the Cedar Street Bridge over Route 9 in the Town of Wellesley. To facilitate construction while maintaining vehicular and pedestrian traffic, the final bridge width will be increased to four traffic lanes with sidewalks on both sides. The work also includes the reconstruction of about 460 linear feet of Cedar Street and about 500 linear feet of Worcester Road and other incidental work. The Cedar Street/Worcester Road intersection will have new traffic signals. Adequate access to abutting property will be maintained during construction.
Location:
  • Town of Wellesley
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2010
    Project Manager: Matt Hopkinson
    Estimated Construction Cost: $6,145,000.00
    MassHighway District: District 4
    Current Status: This project has been advertised for construction bids. (as of 01/16/2010)

    Contracts (2) Progress
    # 33112 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 4 - Contract K Final
    # 59591 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Design Change
    Design change: Lowered Route 9 clearance from 16.5' to 15'
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/04/2003
    Project Review Committee Received 08/18/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 01/16/2010
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 10/21/2003
    Consultant Contract Process Workhours Approved 04/07/2005
    Consultant Contract Process NTP Issued 04/15/2005
    Design
    Highway Design Process 25% Plans Received 11/15/2006
    Highway Design Process 25% Plans Received 02/17/2010
    Highway Design Process 25% Comments to DE 03/31/2009
    Highway Design Process 25% Comments to DE 03/09/2010
    Highway Design Process Design Public Hearing 10/27/2009
    Final Design PS&E to CEPO 01/11/2010
    Final Design PS&E Received 01/08/2010
    Right of Way
    Certification Issued 07/15/2010
    Plans Accepted 01/13/2010
    Requirements Requirements 10/15/2009
    Advanced Title Exam Requested 10/22/2009
    Advanced Title Exam Completed 11/24/2009
    Registry Plans/Instruments Requested 01/13/2010
    Registry Plans/Instruments Layout Schedule Sent 02/02/2010
    Traffic
    25% Design Review 25% Plans Received 02/02/2010
    25% Design Review 25% Plans Approved 01/24/2007
    Design Exceptions
    Environmental
    ITS
    Utilities