AMHERST- RECONSTRUCTION ON ROUTE 116 (WEST ST.) FROM COUNTRY CORNERS RD. TO 800' NORTH OF HAMPSHIRE COLLEGE DRIVE
MassDOT is transferring its ownership of the road to the Town of Amherst so that the town can design the project as local road. The project does include bike path connections, pedestrian accommodation and other amenities at the Atkins Corners location.
Location:
  • Town of Amherst
  • Construction Begins: Winter 2010/2011
    Construction Ends: Summer 2014
    Resident Engineer: Michael McCabe
    Construction Contract Value: $7,034,442.00
    Construction Bid Price: $6,060,220.30
    Initial Construction Estimate: $6,811,756.00
    MassHighway District: District 2

    Contracts (2) Progress
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 66833 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of West Street (Route 116) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/17/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/04/2003
    Project Review Committee Received 10/01/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 03/30/2004
    Project Status Advertised 07/03/2010
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 03/21/2007
    Highway Design Process 25% Comments to DE 06/20/2007
    Highway Design Process Design Public Hearing 06/16/2008
    75% Design 75% Plans Received 02/12/2009
    75% Design 75% Plans Approved 04/23/2009
    75% Design 75% Comments to DE 04/13/2009
    Final Design PS&E to FAPO 07/01/2010
    Final Design PS&E Received 05/25/2010
    Subsurface Exploration 100% Plans Received 11/03/2009
    Right of Way
    Certification Issued 05/30/2010
    Plans Requested 10/06/2009
    Plans Received 12/01/2007
    Plans Reviewed 11/17/2009
    Plans Revised 10/27/2009
    Plans Accepted 12/16/2009
    Requirements Requirements 03/27/2007
    Requirements Requirements 11/17/2009
    Traffic
    25% Design Review 25% Plans Received 03/27/2007
    25% Design Review 25% Plans Approved 06/20/2007
    75% Traffic Plans 75% Plans Received 02/24/2009
    100% Traffic Plans 100% Plans Received 06/01/2010
    100% Traffic Plans 100% Plans Approved 06/03/2010
    Design Exceptions
    Environmental
    Section Cleared 25% Plans Received 12/06/2007
    Wetlands Protection Act Permit Issued 06/09/2010
    Wetlands Protection Act Permit Expires 06/09/2013
    Section 404 (ACOE) Permit Issued 04/13/2010
    Section 404 (ACOE) Permit Expires 01/21/2015
    Section 401 (WQC) Permit Issued 05/14/2010
    ITS
    Utilities
    Non Participating