Project Description:
EASTHAMPTON- BRIDGE REPLACEMENT, E-05-006, ROUTE 10 (NORTHAMPTON STREET) OVER MANHAN RIVER
The purpose of this project is to replace the Northampton Road Bridge over Manhan River. The roadway will also be resurfaced 500 feet north and south of the bridge. The bridge will be closed and traffic detoured during construction. An additional turning lane, north of the bridge structure, will be added for entrance to West Street. The new bridge superstructure will be built with precast concrete deck bulb tee beams to reduce construction time.
Location:
  • Town of Easthampton
  • Construction Begins: Summer 2012
    Construction Ends: Spring 2014
    Resident Engineer: Daniel Kaminski
    Construction Contract Value: $4,422,008.00
    Construction Bid Price: $3,747,747.00
    Initial Construction Estimate: $4,078,154.00
    MassHighway District: District 2

    Contracts (4) Progress
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59590 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 73269 -- Construction Contract
    Bridge Superstructure Replacement (E-05-006) (Concrete) Route 10 (Northampton Street) over the Manhan River. (ABP) 99% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 06/29/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/25/2003
    Project Review Committee Received 09/06/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 04/14/2012
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 01/28/2010
    Consultant Contract Process Workhours Approved 04/16/2010
    Consultant Contract Process NTP Issued 04/16/2010
    Design
    Highway Design Process 25% Plans Received 04/11/2011
    Highway Design Process Design Public Hearing 07/13/2011
    75% Design 75% Plans Received 12/02/2011
    75% Design 75% Comments to DE 01/06/2012
    Final Design PS&E to FAPO 04/11/2012
    Final Design PS&E Received 02/24/2012
    Right of Way
    Certification Issued 04/04/2012
    Plans Received 04/08/2011
    Plans Received 06/09/2011
    Plans Received 08/31/2011
    Plans Received 10/20/2011
    Plans Comments to DE 05/11/2011
    Plans Comments to DE 09/16/2011
    Plans Comments to DE 10/25/2011
    Plans Accepted 02/08/2012
    Requirements Requirements 10/20/2011
    Requirements Requirements 04/01/2012
    Advanced Title Exam Requested 09/16/2011
    Advanced Title Exam Completed 02/14/2012
    Registry Plans/Instruments Received 02/13/2012
    Traffic
    25% Design Review 25% Plans Received 04/20/2011
    25% Design Review 25% Plans Approved 05/13/2011
    75% Traffic Plans 75% Plans Received 12/06/2011
    75% Traffic Plans 75% Plans Approved 02/03/2012
    100% Traffic Plans 100% Plans Received 02/27/2012
    Design Exceptions
    Environmental
    Section 404 (ACOE) Permit Issued 12/20/2011
    Section 404 (ACOE) Permit Expires 07/31/2015
    Section 401 (WQC) Permit Issued 12/20/2011
    ITS
    Utilities
    Non Participating